INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Oil and water storage tanks Bottom plate Replacement

Oil and water storage tanks Bottom plate Replacement

Oil and water storage tanks Bottom plate Replacement

(OP)
Dear All,

I am working in oilfield. Our company is trying to get some new job and it's very good opportunity and new work for us. We have to replace the bottom plate of oil and water storage tanks. I have done research and had many discussion with few experts whom i know. I am here to get more information about it. We have various size of tanks which starts from 9 meter Dia to 36 meter dia tanks respectively height is from 5 meter to 15 meter. I have found two method for replacing the existing bottom plate which is as follow.
1. Hydraulic Jack Lifter
2. Double Bottom.

From above this two method Hydraulic jack lifter method is expensive and time taking method for this job while Double bottom is less expensive and very less time consuming.
I want to get more details about these two method so, if anyone have any information like Detail Procedure or any kind of reference document then kindly please share with me and also give your ideas about the same so, we can execute this job smoothly.

It would be appreciated and will be thankful to you for this.

BR,
Satish

RE: Oil and water storage tanks Bottom plate Replacement

Once the tank is safe for welding, the general practice is to first cut out a panel for access to the tank.

Then, C clips are welded around the tank perimeter base to hold the tank shell while the bottom is being replaced. Next, a cutting torch on a track rotates around the tank to cut off the bottom at the c clip. The new bottom plates are slipped under the tank and welded.



Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources