INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

For 2 TJI joists ends touching free

For 2 TJI joists ends touching free

For 2 TJI joists ends touching free

(OP)
For 2 TJI joists ends touching freely at a point resting on top of a beam, should any special connections (web stiffener?) be used if only top-down forces are acting on the TJI joists? The TJI joists will have roofing resting on the top flange. Thank you

RE: For 2 TJI joists ends touching free

Depends on the end reaction, the bearing length, and the TJI size. Check with the manufacturer's literature, everything you need should be there.

RE: For 2 TJI joists ends touching free

Is there a wood nailer on top of the beam? How are the TJI's attached to the beam?

Dik

RE: For 2 TJI joists ends touching free

Generally I would want to have blocking to prevent rotation at the bearing ends (much like a rim joist would do at an "outside" wall.
That might even be a manuf. requirement.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources