INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

EPAnet 2.0 and multiple demands

EPAnet 2.0 and multiple demands

EPAnet 2.0 and multiple demands

(OP)
Hi, does anyone who is familiar with EPAnet 2.0 aware of any way to have an easy way to change demands from year to year without making multiple models?
I was looking at demand categories but I don't know if that would work.


Thanks

RE: EPAnet 2.0 and multiple demands

492

Demand categories will do the the job, use the time pattern to adjust the demands in that category as your annual adjustment
eg set a base demand, make the demand category all the same on the demands you want to adjust, then use the time pattern as a multiplier, and consider each hour a new year. You may be able to change the default time from 1 hour to 1 year.

Hydrae

RE: EPAnet 2.0 and multiple demands

(OP)
Thank you for the reply.
Is that the only way or could I have 4 categories that are my different years and I choose the category/year and all the demands will change to the corresponding category automatically?

Thank you

RE: EPAnet 2.0 and multiple demands

have 1 category and run the model for 4 'hours' each hour is the year
each demand can have only 1 category but nodes can have more than 1 demand.
as an example
at a node you can have a domestic, irrigation and fire demands each demand would have its own category each category has it on time pattern
the default time step is an hour so each hour can be considered a year.
or if you want increase the time step to 8760 hours and you got your 'yearly' adjustment

RE: EPAnet 2.0 and multiple demands

(OP)
Okay, Thank you.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources