Hello everyone,
I started my own firm back in September of last year, and I've been slowly figuring out the art of pricing structural engineering work. I recently met my first potentially large client, and I am trying to put together a quote for him. I don't really have any mentors here in town I can turn to with these kinds of business related questions, so I am hoping that I can crowd source some help on this one.
The project is located in Texas, and consists of a 3 story metal building supported by a boat dock. The boat dock will be designed by another company so, essentially, it's just a 3 story metal building with foundation by others. I have attached the preliminary drawings for reference. I have a figure in mind already, but I'd like to get a sense of what the market bears on something like this. I would hate to underbid this project because of obvious reasons, but also because I would hate to contribute to the reduction of engineering fees in my region. Any input will be greatly appreciated. Thank you all in advance for your time.
Christopher C.
P.S. If any of you business veterans out there have any resources for small firm owners you can point me towards, I'd love to hear about them.
I started my own firm back in September of last year, and I've been slowly figuring out the art of pricing structural engineering work. I recently met my first potentially large client, and I am trying to put together a quote for him. I don't really have any mentors here in town I can turn to with these kinds of business related questions, so I am hoping that I can crowd source some help on this one.
The project is located in Texas, and consists of a 3 story metal building supported by a boat dock. The boat dock will be designed by another company so, essentially, it's just a 3 story metal building with foundation by others. I have attached the preliminary drawings for reference. I have a figure in mind already, but I'd like to get a sense of what the market bears on something like this. I would hate to underbid this project because of obvious reasons, but also because I would hate to contribute to the reduction of engineering fees in my region. Any input will be greatly appreciated. Thank you all in advance for your time.
Christopher C.
P.S. If any of you business veterans out there have any resources for small firm owners you can point me towards, I'd love to hear about them.






RE: Pricing Help
Project Value,
Number of Drawings Prepared, and
Estimate of the Amount of Time required to do the work.
Project value is used to determine the fee based on a percent... depends on local and experience. The number of drawings fee is based on 40 hours per normal sheet, 50 hours for detailed sheets and 12 hours for drawing notes; there may be 4 or 5 drawing notes sheets. I tend to put lots of information on the drawings... not much 'white' space. I don't like 3 part specs. The third item is based on how much time you need for doing the project. The three numbers will give you an idea of what the fee should be.
If specs are required I usually budget 4 hours per section. Construction review and testing is on top of this as well as preparation of bid documents. Also if there are specific requirements that are time consuming... like weekly project meetings that run a whole day, etc.
Hope that doesn't confuse you too badly.
Dik
RE: Pricing Help
EDMS Australia
RE: Pricing Help
Dik
RE: Pricing Help
RE: Pricing Help
and, Welcome to the site.
Dik
RE: Pricing Help
You'll get the hang of it though. Take dik's advice. Approach the thing from 3 separate angles and if the values don't converge at all, try to reason out why.
I would also suggest a rough estimate of $2500 per drawing, if you can get it, just as a starting point. This is pretty accurate for most of the work I do. But still, for every project I begin by defining a scope of what's required, and putting a reasonable # of hours to it. Where I make my money is by improving on the hours expectations.
If you're hungry and want to attract a client, lower your price a bit. If it looks like a PITA, add a complexity factor. Don't sell yourself short, and don't be OVERLY concerned about overpricing. In my experience a reasonable client will talk to you about the price rather than being offended at your audacity. Whereas if people are bringing you on board willy-nilly you're probably charging too little.
Good luck!
RE: Pricing Help
Dik
RE: Pricing Help
Now maybe you're willing to work for $28/hour to get your business off the ground. You bust tail, and get a good rolodex of clients. You're going to be the structural equivalent of Microsoft. It's time to hire your first employee. You might get a minimally skilled CAD operator for $28 an hour. But minimally skilled means more checking and spoon feeding, eating into your 50 hours. And for sure you're not getting an engineer for $28 an hour.
If all your drawings have a lot of typical details and your work is routine, with standard notes and the such, maybe $2500 works. But if you're spending 50 hours on them, you're going to be applying for a job with me pretty quick.
Back to the OP. Our numbers are pretty close to dik's. Say 40 hours a sheet, (20 Engineering and 20 CAD) plus something for specifications and general notes. Apply your salary and that of your employees times a multiplier. This multiplier can vary between 1.8 (working in a cardboard box, no training budget, very minimal perks, no Christmas party) and 3.2 (what a specialist gets, Class A space, separate business development budget, open bar at the Christmas party) and that's your price per sheet.
RE: Pricing Help
TTFN (ta ta for now)
I can do absolutely anything. I'm an expert! https://www.youtube.com/watch?v=BKorP55Aqvg
FAQ731-376: Eng-Tips.com Forum Policies forum1529: Translation Assistance for Engineers Entire Forum list http://www.eng-tips.com/forumlist.cfm
RE: Pricing Help
That's what our company's multiplier is... but, just for the plebes... the shareholders see the benefit... and we live like the 1.8 multiplier. Our IT department 'skims' off $5 for each hour for each employee... and if they spent the money on equipment, it would reduce their profit... I generally use my own laptop and upload work at the end of the day/week; I can be working on mine before the company desktop has reached the login screen.
Dik
RE: Pricing Help
If OP is doing the design and drafting themselves, using a blended rate of about 100 bucks for eng/drafting, that's 25 hours of 'work' that one can likely do in 5-10 hours. So you're not paying yourself as little as you think for doing lump sum work. But indeed established companies with built up reputations and good client relationships can get away with charging more.
Also, as we know, 'a drawing' can vary greatly in complexity and effort. It's important to note that if the number of drawings isn't representative of the amount of effort required to complete the work, then it's an equally poor representation of what you should be charging.
RE: Pricing Help
That's the reason for looking at pricing from 3 different methods... Drawing count is not a bad representation of actual costs. After a period of time, you can get to price using drawing count and value, quite well. It's also something that you can accumulate a metric from past work.
Dik
RE: Pricing Help
If we assume ANSI D or E drawings, then I can imagine the following sheets:
- First Floor Framing
- Second Floor Framing
- Roof Framing
- Sections
- Details
At $2500 each, we're looking at a $12,500... maybe $10,000 if we get sections and details on one page.The method I've been using so far has been based on time estimates @$1200/day with a resolution of 0.5 days. Thus:
- RISA model and large member optimization... 1 day
- Sub-floor, roof cladding, and/or slab design (3 levels)... 1 day
- Stud framing, Bracing, and headers... 1 day
- Misc:
- Elevator Hoist Beams... 0.5 days
- HVAC Framing... 0.5 days
- Railing... 0.5 days
- Stairs... 0.5 day
5 days @$1,200/day yields $6,000 ==> Double that to include drafting time ==> That's $12,000Hey!... pretty close results
How does that all look to the rest of you. Do you think I might be missing something?
RE: Pricing Help
RE: Pricing Help
Dik
RE: Pricing Help
-If it's one of your first projects and you're happy with the fee, go for it. You'll know at the end of it if you charged enough or not.
-Keep track of how much time it actually takes you and make adjustments in the future.
-One of the most intimidating things when you start out is submitting a price and then flipping out for days before you hear back terrified that it was too much. This is certainly a concern of sorts but at least in my opinion is a bit overrated. More often than not, if you've thought it through, you're in the right ballpark. Relax, and wait to hear back.
RE: Pricing Help
Dik
RE: Pricing Help
Does anybody know of any resources that address the pricing of engineering services?... I've looked around, but I haven't had any luck. I know there is quite a bit of literature on construction estimating, but there's nothing I've really seen on design and/or engineering.
RE: Pricing Help
Dik
RE: Pricing Help
Dik
RE: Pricing Help
Design & Build
Rule #1 - Know your costs... Sounds easy.. It is not... Need to spend a significant portion of your career evaluating the costs of performing the work. Keep historical data. Keep lessons Learned. Keep pace with changes in the market; both cost changes and changes in the way things are done. Evaluate your performance after the project is complete.
I simply summarize costs and add a margin that I feel is reasonable considering all the variables..
These include: Risk, Manpower, how close is the project's technical requirement aligned with your firm's skill set, Can you find out the price range that you competitors are in, Don't leave out the costs of training your people and mentoring replacements for when your people retire (this one has recently become a challenge for me). Watch out for inflation! This one is coming. I've survived a few recessions and expansions where inflation was a big cost hit. Beware.
Lastly... I find that pricing jobs is easy once the scope of work is clearly defined... but all too often, the scope of work is not clear and it leads to disagreements with both clients and service providers. I cannot stress enough that all contracts should clearly state what is included and excluded.
Never underestimate the value of an estimator
Best regards
RE: Pricing Help
I use this exact method. I also track square footage costs and building types. I.e., wood framed, steel, concrete, PEMB foundations, equipment foundations, etc. With several projects under your belt of each type, you will hone in on accurate project costs.
About profit margins: you should have an idea of tracking overhead costs as they relate to profitability. Basically, your overhead costs need to be smaller than the difference between your billing rate and direct hours billed. Otherwise, you won't make any money. For example, if you bill out at $100/hr, and your salary is $50/hr, then your overhead costs need to be less than $50/hr for every hour worked. That shouldn't be a problem. Say that with overhead factored in, your cost to the company is $70/hr. Then, for every project you complete on time with the exact budgeted hours worked, you make the company $30/hr profit. Make since? That is about 30% profit for each project. This is a real rudimentary example not considering interest, taxes, depreciation, etc. But with this profit margin, you can afford to lose your shorts once in awhile intentionally or unintentionally.
RE: Pricing Help
The biggest source of cost over runs... Catch a recent eMail of mine on a project...
I'd pretty much closed the door on this project... it was started in Sept, 2015 and it's almost Mar, 2018. It is likely vastly over budget.
The last 18 or so hours I haven't bothered to bill for because of budget conditions. It's been a dismal project.
When I did the Cornwall Centre in Regina, I was on it for 3 years and did [xxx] all in the same time.
I hope they fab it and install it without issue; it's simple and there should be no problems. The documents are well prepared. Its minimal area limits its use.
The only thing outstanding is the energy efficiency and compliance with the National Energy Code for Buildings. Doug of [xxx] should be able to look after that. I started a spreadsheet for calculating R values and sent it on months back.
Good luck with it.
Sometimes, even if you know what you're doing... ya get sucked in... beware of the fan... It was a small building and should have taken less than a month...