×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Doweling into existing slab

Doweling into existing slab

Doweling into existing slab

(OP)
I have a situation where a new slab is going in between two existing ones. There are dowels going into the left hand side, because those slabs will be sharing the same load. My questions are as follows.

1) Does the new slab have to be doweled into the existing slab on the right? Could surface preparation and vertical dowels through that cantilever section be enough? Or does it need shear dowels to connect the two. Intuition tells me it does, or differential settlement will cause that cantilevered piece to break off.

2) If the slab needs to be doweled in on that side I am concerned that the new dowels will hit the existing stirrups. Is there a good way to word how to avoid this on the design drawing? "Dowel every 12 inches, if existing bar is struck move x inches and continue pattern"?

RE: Doweling into existing slab

(OP)
Perhaps I should reform the question. I know I need to dowel into the existing slab. I am worried about striking existing bar and damaging the existing pad. How can I limit the damage of existing pad/bar while installing the new dowels? Should I specify abandoned holes to be filled?

RE: Doweling into existing slab

First, you have too many dowels. You only need one in cross section. It should be one inch in diameter, hardened steel, smooth and one side should be greased to allow lateral movement from shrinkage and thermal movement. As for the cantilevered section....get rid of it!. Sawcut the existing concrete back to a vertical surface and dowel in as on the other side.

RE: Doweling into existing slab

(OP)
Understood for one dowel. I am not sure why I drew it like this.

The reason I am not cutting the existing concrete to vertical is because there is an operational rail on top of it. This addition stretches a fair distance length-wise and I would need to tear up the rail and replace it if I were to do this.



RE: Doweling into existing slab

(OP)
It's 3'. It's thicker than the slab on the right by 10".

RE: Doweling into existing slab

For a slab (more like a mat) that is 3' thick, there must be significantly heavier loads than a semi truck as you show. If that's the case, I would suggest more than 1 dowel to transfer the load.

RE: Doweling into existing slab

(OP)
I'm sorry. The new slab is 3' and is thicker than the one on the right by 10". The trucks are carrying much heavier cargo than typical applications.

RE: Doweling into existing slab

LeonhardEuler - Per MotorCity's comment, a "slab" that is 3' thick must have tremendous loading. The only commercial applications that I know of may be runways for the heaviest aircraft or a shipping container terminal / intermodal rail yard. IMHO, dowels could do more harm than good for this retrofit project... slab settlement under load could cause any reasonable number of dowels to shear or crack concrete. I would not use any.

Suggest getting an experienced geotech involved to design the subgrade. Even then, any needed excavation / backfill will be a challenge to keep from undermining the existing concrete. Predict the slab's settlement and construct with the finish surface "high" by that amount. To make construction somewhat easier, don't try to place the entire 3' thickness in one placement. If calculations permit, use a substantial overlay for the finish surface. We have used this type foundation / overlay approach on the heavily loaded portions of our electric generating stations.

Expansion / isolation joints allow the new concrete to settle without disturbing the existing concrete on either side. Omit the proposed cantilever.



www.SlideRuleEra.net idea
www.VacuumTubeEra.net r2d2

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources