INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

ASME VIII DIV 1 - Consumable Pre-Test UHA51

ASME VIII DIV 1 - Consumable Pre-Test UHA51

ASME VIII DIV 1 - Consumable Pre-Test UHA51

(OP)
Hi,

Wondering if any one can help on the following matter.

We’ve been asked to construct a vessel with a MDMT of -196 deg c constructed from SA240. Welding consumables are AWS 5.9 and AWS 5.22 308l. After reading through UHA51 numerous times I have come to the conclusion that we are required to perform pre use testing on the wire batches. In other words toughness testing on them both and achieve lateral expansions equal to or greater than 0.38.

However our inspector is requesting that we also perform tensions and bends as part of the pre use test. I have read over subsections ug, uw, and uha, can’t seem to find where he isn’t pulling this request from.

If any one has any ideas I would be grateful.

Thanks,

RE: ASME VIII DIV 1 - Consumable Pre-Test UHA51

You are correct. Why not have the welding consumable vendor supply pre-use testing results in the mill test reports?

RE: ASME VIII DIV 1 - Consumable Pre-Test UHA51

DEAR PVTC
You need to satisfy all the conditions UHA-51(f)(1) thru UHA-51(f)(4).
Since you are using GTAW, UHA-51(f)(1) is satisfied
You need to have PQR done with impact tests to satisfy UHA-51(f)(2)
Since you are using ER308L, UHA-51(f)(3) is satisfied
For GTAW, applicable paragraph is UHA-51(f)(4)(-e) which states that ER308L may be used WITHOUT PRE USE TESTING of each heat and/or lot, provided that procedure qualification impact testing in accordance with UG-84(h) have been performed.

You have two choices
Make PQR with impact tests at -196C, get exemption from pre-use test for ER308L. However you will need a production impact test as per UHA-51(h)(2)(-b).
Alternatively Make PQR with impact tests at -196C, also perform pre-use tests and get exemptions from production impact tests.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources