INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Cable Route guidelines

Cable Route guidelines

Cable Route guidelines

(OP)
How to approach cable routing for HVAC works? Should it be started after or before the duct layout has been prepared? How the clashing between cable tray and duct, pipelines can be avoided?

RE: Cable Route guidelines

Construction coordination is the job of the General Contractor.

RE: Cable Route guidelines

Ductwork above ceilings should have very few vertical transitions; having unnecessary bends and transitions makes the fan work harder and the system becomes less efficient. The cable trays I've seen are always run at an elevation below the ductwork all but eliminating conflicts. Then during construction, the GC will offset small duct branches, piping and your cable trays as needed to make everything fit.

To answer your question, it does not matter.

IF you are that concerned about conflicts, the best thing to do is layout where you want the cable trays then talk to the HVAC designer to coordinate.

Being in a position where I frequently review designs, I cannot tell how how often I've seen plans where it is clear the engineers and architects have not coordinated with each other. It's as if they are each in their own little worlds.

RE: Cable Route guidelines

Will your designers not be modelling the system in 3D? I have noticed that with everyone working within the same model (or space) any conflicts will be identified and remedied long before they become a problem in the Field.
If you are not all working in the same model, you obviously must have good communications, and have designers who care about their work.
GG

"I have not failed. I've just found 10,000 ways that won't work." Thomas Alva Edison (1847-1931)

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources