Does the hydrotest include piping systems that will be connected to the final product?
Does the hydrotest include piping systems that will be connected to the final product?
(OP)
Hello,
I am designing a pressure vessel according to Division 1 rules that will eventually be fed steam via a piping system. Does the hydrotest require that the piping be included, or can that be tested independently? Nothing is said about piping in UG-99.
Thanks.
I am designing a pressure vessel according to Division 1 rules that will eventually be fed steam via a piping system. Does the hydrotest require that the piping be included, or can that be tested independently? Nothing is said about piping in UG-99.
Thanks.





RE: Does the hydrotest include piping systems that will be connected to the final product?
See U-1(e) for what is included in scope of vessel (Sec. VIII Div.1)
RE: Does the hydrotest include piping systems that will be connected to the final product?
RE: Does the hydrotest include piping systems that will be connected to the final product?
RE: Does the hydrotest include piping systems that will be connected to the final product?