INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

SAP 2000 Cold formed steel design( difference of ratio between members)

SAP 2000 Cold formed steel design( difference of ratio between members)

SAP 2000 Cold formed steel design( difference of ratio between members)

(OP)
Hello everyone,

please find attached the issue that i met during my design of a 15 m portal in cold formed steel using deep C 200x2,5mm sections for beams and columns

anyone can tell me why i have this difference in ratio between the two sides of portal.

thanks

Islem

RE: SAP 2000 Cold formed steel design( difference of ratio between members)

(OP)
hello everyone;

i am designing a shelter which has dimensions of 6m of width and 25m of length and 6m of height the my section for beams and columns is C200x40x11 (back to back)(2,5 thickness) ,during my vérification in accordance with AISI LRFD i found out that some columns have verified and some have not ,for beams none item has checked (O/S error) .
Please i wonder if there is any solution i can use , note that i have inserted the unbraced length ratio for all members.
.
thanks and best regards
islem.

RE: SAP 2000 Cold formed steel design( difference of ratio between members)

Are you a structural engineer ?

RE: SAP 2000 Cold formed steel design( difference of ratio between members)

(OP)
yeah i am but i am new in cold formed steel why ?

RE: SAP 2000 Cold formed steel design( difference of ratio between members)

Those sections would be no where near adequate based on gut feel alone.

Are those envelope results you've posted, or just a single load case?

RE: SAP 2000 Cold formed steel design( difference of ratio between members)

(OP)
@jayrod12 yeah they are the enveloppe beams and column results .
about sections i know that are not adequate but when i desiegned a frame portal which has 12m of width all the members have been verified.
thank you very much for your help jayrod.

islem

RE: SAP 2000 Cold formed steel design( difference of ratio between members)

If it's an envelope run, then I would expect them to have the same max code check values assuming the loading is uniform.

If the loading is uniform then I would look at each members design parameter, I.e. unbraced lengths.

RE: SAP 2000 Cold formed steel design( difference of ratio between members)

(OP)
Dear jayrod;

I checked another time and increased the section to C250x65x20 2,5 thickness the ratio has reduced a lot.

thanks for your help

regards

islem

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources