INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Requirement for shop drawings

Requirement for shop drawings

Requirement for shop drawings

(OP)


Situation: Basically, I am engineering the attachment of a sign cabinet to an existing concrete base. The fabricator doesn't know exactly how they are going to build the cabinet yet, but I want so ensure that whatever they do actually conforms to the basis of design I used to create my anchor loads and specs so the load path works out, etc.

It is industry standard and acceptable to cities for things this small to just have the primary anchorage or foundation engineered. Let's not get bogged down on that issue.

What I want to know, is if there are any standard verbiages that I could put on the front of my drawings that basically say "hey! Fabricator needs to submit proposed shop drawings prior to production so engineer can verify they conform with the basis of design used in this analysis."


Thoughts?


RE: Requirement for shop drawings

Two thoughts.
(1) If you have general notes, put a general note on stating something to the effect of "Submit Shop drawings/fabrication drawings of cabinet showing (i) connection locations to foundation, (ii) total weight, (iii) location of center of mass, (iv) ...." etc. I would be really specific and only require that information you need to in order to verify compliance with your design scheme.
(2) I would document the basis of design if possible. Telling the manufacturer where you expect attachment and what loads you are expecting will give them the best chance of getting it right initially. Optimally, they would force their design to conform to your criteria. If that is not the case, it may facilitate a phone call where you can work things out without going to iterations of the approval process.

Robert Hale, PE

RE: Requirement for shop drawings

First guy in the ground and last to get the information.

Draw a picture of the loading scenario assumptions and stick it right next to your stamp.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources