Datum Shift
Datum Shift
(OP)
Folks
I am confused about datum shift. In the counterbore stack, we see them bilateral in Line D & P. But in the other stack, they are bilateral unequal, Line E. Is 0.1/.005 come from the perpendicularity control. Also, Where Line F, G, Line J, K come from. The position tol has been accounted already in Line B&N
thanks
I am confused about datum shift. In the counterbore stack, we see them bilateral in Line D & P. But in the other stack, they are bilateral unequal, Line E. Is 0.1/.005 come from the perpendicularity control. Also, Where Line F, G, Line J, K come from. The position tol has been accounted already in Line B&N
thanks





RE: Datum Shift
But for the longer stack that was attached to your post, the datum D is only used in the stack for its axis; the stack path never touches the wall of that through-hole. Thus the size variation of the datum feature doesn't play a role in the shift.
If you have the textbook where those exercises are taken from, look back to a page in the bonus & shift chapter which shows a "bonus/shift chart." (In my version, it's on page 12-3.) The right-hand side of that chart explains how to enter the shift tolerance in the stack. Your shorter exercise would be considered stack condition 2 and your longer exercise would be considered stack condition 1.
John-Paul Belanger
Certified Sr. GD&T Professional
Geometric Learning Systems
RE: Datum Shift
I know I am missing something simple, but what do SU and ACT stand for?
The embedded graphic phrases the question oddly - "What is the max and min wall thickness?" would have been more clear.
The main thing is that the wall thickness problem is not symmetric, so the tolerance is not symmetric.
The counterbores are equally disposed from their true position at their maximum and minimum so the tolerances are equally disposed.
FG,JK come from the individual position tolerances on the c'bores. There are two holes and two counterbores, each with a bonus and shift, so that should be eight lines on the analysis, which is how many lines are used for them on the table.
RE: Datum Shift
You can tell this drawing uses the 1982 standard, and even back then paragraph 5.3.6.2 recognized simultaneous requirements, so the note wasn't really needed. However, I think for a while General Motors (from whence Alex came) had an internal rule about separate requirements being the default -- I don't exactly recall. So apparently he felt it's safer to just add the simultaneous req't note.
John-Paul Belanger
Certified Sr. GD&T Professional
Geometric Learning Systems
RE: Datum Shift
thanks Belanger.
RE: Datum Shift
I am using VC and RC boundaries to calculate the stacks.
For the embedded picture I could get the same results as the ones shown in the book (max and min calculations match), but for the attached one (stack shown in the attachment and the more complex one) I am not ABLE to get the same results. I have no idea what I am missing.
Maybe the stacks CANNOT be done using VC and RC for this particular circumstance? Could you help?
Since the C'bore are references to D (at MMC/MMB) and the holes are to A primary and B secondary (at MMC/ MMB), could that be a reason on why Vc and RC does not work or most likeliy I have done something wrong.
RE: Datum Shift
I'll have to take some time tomorrow to try that longer stack using your method...
John-Paul Belanger
Certified Sr. GD&T Professional
Geometric Learning Systems
RE: Datum Shift
RE: Datum Shift
CODE --> aniiben
Do you mind posting the stack so others can chime in?
RE: Datum Shift
The VC/RC approach will work only if these extreme boundaries exist within one frame of reference and no other datum systems are involved in calculations. It is true in case of embedded stack-up because everything is calculated within datum system created by primary datum feture A at RMB and secondary datum feature B at MMB, but is not true for the attached stackup. In this stack-up different frames of reference are involved [D(M) and A|B(M)] thus if you want to use the VC/RC approach you should also add to the stack-up tolerances that come from geometric characteristics that control relationship between datum feature D relative to A|B(M).
It is just a guess, but are your calculated values 46.5 for MIN distance and 47.9 for MAX distance? If that is true it is because you have not taken into account the fact that each individual datum feature D has its own position tolerance relative to A|B(M) that gives extra 0.4 of radial displacement for each of the two holes D when produced at LMC, AND most likely you have not taken into account two radial datum feature D shifts of 0.4 that will be possible in case of positional tolerances for c'bores, because each c'bore is positioned indiviudally to its corresponding datum hole D.
This in total gives extra 1.6 of tolerance which needs to be subtracted from 46.5 in case of MIN distance calculation, and added to 47.9 in case of MAX distance calculation.
RE: Datum Shift
However, it doesn't work with the longer stack. The reason is that the longer stack uses only the axis of datum D in the calculation -- not the actual wall of that datum feature. If you do a simple sketch of any VC or RC, you'll notice that it's all about finding where the wall of the feature lies. But when we are stacking only axis to axis (such as from one datum D to the other datum D), the VC and RC are less relevant.
I just read pmarc's post and I think this is the same idea he was saying.
John-Paul Belanger
Certified Sr. GD&T Professional
Geometric Learning Systems
RE: Datum Shift
If, for example, in the longer (attached) stack both c'bores were positioned to A|B(M) (i.e. gaged simultaneously), it would be okay to subtract two times the radius of c'bore RC from basic 60 to get minimum possible distance between the edges of the c'bores. And consenquently, it would be okay to subtract two times the radius of c'bore VC from basic 60 to get maximum possible distance between the edges of the c'bores.
So we would be able to apply VC/RC approach even though we never used actual wall of datum feature (B in this case). We would be able to apply VC/RC approach because these extreme boundaries were positioned relative to the very same datum reference frame.
RE: Datum Shift
I am trying to understand what I am missing....did not fully get it yet...... and to be honest I am also using
Subject: Query regarding Wall thickness calculations
http://www.geotolmeadows.com/newsletters/2007/aug2...
and
Subject: Question on Book-Minimum Wall Thickness Calculations Using Tolerance Stack-Up Analysis
http://www.geotolmeadows.com/newsletters/2012/nov2...
Are those good references for what we are talking about here or just create more confusion...?
Thank you pmarc for your input
RE: Datum Shift
The Excel file that I posted earlier is an attempt to bridge those two methods: It sort of looks like Krulikowski's spreadsheet, but it was tweaked to allow the nominal (either positive or negative) and then the plus/minus numbers to be entered.
This worked fine for the shorter (embedded)stack in the OP. But pmarc -- my concern on the attachment stack really was about the axis-only idea in the shift, because this tweaked version of the spreadsheet doesn't have an easy way to capture that. Take a look at the file attached to this post, and you'll see what I did to make the answer come out correct. I used VC/RC for the two counterbores, but to relate each datum D back to datum B, I just lumped all of the error into the jump of 60 across the bolt circle. Yes I got the correct answer, but it doesn't use the VC/RC of the datum as we would normally try to do with that method.
John-Paul Belanger
Certified Sr. GD&T Professional
Geometric Learning Systems
RE: Datum Shift
No doubt that both are correct. How to wrap my head around these calculations that is another story.
RE: Datum Shift
For the case of the distance between counterbores (PDF attached in original post), here are my attempted calculations:
I didn't try terribly hard to decipher the original calculations, but I believe lines D and P are the cause of the disagreement. It's as if they used a MMB of diameter 5.6 instead of diameter 6.2 for datum features D. I'm not sure why that would have been done, considering the counterbore position tolerance references datum feature D as primary. Perhaps someone can offer some insight.
Note that the above assumes perfect form and orientation for all features. If the effects of orientation errors are considered, the answers change drastically.
pylfrm
RE: Datum Shift
I agree with you. Since datum feature D is referenced primary at MMB in the position callout for c'bores, radial amount of datum feature D shift should not be 0.4 [(6.4-5.6)/2], but 0.1 [(6.4-6.2)/2] instead.
But this (no reference to A primary in the position callouts for c'bores), as you noted, adds another complexity to the problem. For both MIN and MAX calculations, tolerances coming from each individual hole D-c'bore pair should not be considered in the direction parallel to datum plane A, because each individual datum axis D may be rotated within position tolerance zone applied to datum feature D. This means that position tolerance zones for c'bores, which are perfectly centered at corresponding datum axes D, don't have to be parallel to each other in the end. If they don't have to be parallel to each other, the only way to really find MIN and MAX distance in question is to include depth of the c'bores and thickness of the shoulder in the calculations.
RE: Datum Shift
Would the stackup change if “4 x individually” note would not be there (delete this note from the counterbores size requirements)?
Will simultaneous requirement be now (after “4 x individually” note is gone) implied for the counterbores or it’s implied anyway?
RE: Datum Shift
Thank you
RE: Datum Shift
Good point about the datum axis orientation issue. I should have included perfect datum axis orientation in my list of assumptions.
In the original drawing, the four counterbore position tolerances are not part of a simultaneous requirement because they do not have common datum feature references (despite using a single datum identifying letter). Removing "4 X INDIVIDUALLY" AND "4 PLACES INDIVIDUALLY" will make datum feature D into a single pattern of four holes, and the four counterbore position tolerances will apply as a single simultaneous requirement. The answers would then be 46.5 and 47.9, again ignoring the (now relatively small) effects of orientation errors.
If datum features D are referenced RMB, the datum axis in each hole will no longer be able to shift in whatever direction minimizes or maximizes the value of X.
pylfrm
RE: Datum Shift
pylfrm,
Are you sure that if only "4 X INDIVIDUALLY" AND "4 PLACES INDIVIDUALLY" are removed from the problem statement/ drawing then the "new values" are the ones you indicated in your above quote?
I am not saying that you are incorrect, it's just seems strange to me.
As pmarc indicated earlier, the values 46.5 and 47.9 (for minimum and maximum X distance, respectivelly) are when---see pmarc's quote below
.... again....I know for sure I am missing something.....not sure what.
[quote pmarc][/It is just a guess, but are your calculated values 46.5 for MIN distance and 47.9 for MAX distance? If that is true it is because you have not taken into account the fact that each individual datum feature D has its own position tolerance relative to A|B(M) that gives extra 0.4 of radial displacement for each of the two holes D when produced at LMC, AND most likely you have not taken into account two radial datum feature D shifts of 0.4 that will be possible in case of positional tolerances for c'bores, because each c'bore is positioned indiviudally to its corresponding datum hole D.quote]
RE: Datum Shift
And to follow up on my own question, what would be the new values (X min and X max) if D is RFS?
RE: Datum Shift
The closest (to the “correct” book values) Xmin and X max values that I can came up with are:
Xmin: 45.7 and
X max. : 48.7.
I’m missing 0.8 from each value to get to the book values.
Not sure where the additional 0.8 should be driven from, but here are “my” calculations:
X min: 59.2 - 13.5 = 45.7
59.2 = 60 - 0.8 (max bonus on D)—max bolt circle diameter located at 60 basic )
13.5 = resultant condition for the c’bores
Xmax: 60.8 - 12.1 =48.7
60.8 = 60 + 0.8 -minimum bolt circle diameter located at 60 basic
12.1 = virtual boundary for the c’bore
My values (Xmin: 45.7 and X max. : 48.7) are closer to pylfrm’s values ( Xmin: 45.5, Xmax: 48.9), but nevertheless still a difference.
0.2 would be the differences between pylfrm’s values and mine.
If one of the experts can explain where this discrepancy came from I will greatly appreciate that. I am learning tolerance stackup. Not sure I will ever understand it completely.
RE: Datum Shift
First, the key input for the discussion is pylfrm's post from 25 May. Up to that point I had been too focused on trying to explain to aniiben the difficulties/limitations of VC/RC approach in stack-up calculations that I simply missed one very important thing - the counterbores in question are positioned individually to D(M), not to A|D(M), which in consequence means that the calculations shown in the workbook are... how to put it... wrong. One thing is that the datum feature shift values in rows D and P shall not be 0.4, but 0.1 instead. And additionally, even with the values in rows D and P corrected, we would have to make a bunch of assumptions about perfect orientation of considered features relative to each other, which is not what we are told to do. To be able to calculate Xmin and Xmax correctly (without a need of making any assumptions), we would have to know the flange thickness and would have go into trygonometry - this is what I tried to explain in my post from 26 May.
Also, assumptions would not have to be made, in my opinion, if the positional callout for counterbores was referencing |A|D(M)|. In that case correct answers would be Xmin = 45.5 and Xmax = 48.9, as given by pylfrm.
------
Then some follow up questions were thrown in, which essentially have been also answered by pylfrm:
1. What would happen if '4X INDIVIDUALLY' and '4 PLACES INDIVIDUALLY' notes were removed (aniiben)?
Then the position callout for counterbores would be treated as simultaneous requirement meaning that no datum feature D shift would be included in the calculations (line D and P from the original stack would be 0). Additionally, since the stack would not need to include position tolerance of thru holes D relative to datum axis B, unlike in the original stack, lines F, G, H, J, K, L would go away. That would result in Xmin = 46.6 and Xmax = 47.9.
2. How will the stackup will change if datum feature D is called RMB (greenimi)?
If the question is about modification of the original stack, not modification of aniiben's modification, datum feature shift values in lines D and P in the original stack shall be 0. This gives Xmin = 47.4 and Xmax = 48.7. Again, these values are true if assumptions about perfect orientation of all considered features relative to each other are made.
If the question is about modification of aniiben's modification, the answer is Xmin = 46.6 and Xmax = 47.9. So this actually means that it does not really matter what material boundary condition (MMB, LMB or RMB) the datum pattern D is referenced at in the positional callout for counterbores - Xmax and Xmin values stay unchanged. It is because the stack is calculated between features that are gaged simultaneously in both cases.
3. And finally, aniiben's question about missing things in his/her calculations/thought process that result in Xmin = 45.7 and Xmax = 48.7.
The difference of 0.2 in both cases comparing to pylfrm's answer comes from the fact that you did not include two radial datum feature D shifts of 0.1 that are possible if both individual thru holes are made at LMC [0.1 = (6.4-6.2)/2].
RE: Datum Shift
I stand by my answers of X_min = 60 + 12.1 - 2 * 12.8 = 46.5 and X_max = 60 - 12.1 = 47.9. I don't know why pmarc has X_min = 46.6.
Here are my calculations:
I don't know why pmarc has X_min = 47.4.
Note that the assumption of perfect form is important here. Non-cylindrical through-holes would allow the answers to remain arbitrarily close to 45.5 and 48.9.
As pmarc said, it is because you did not include datum shift. Note that your answers match mine for greenimi's RMB scenario.
I disagree here. Referencing A as primary changes the MMB of datum features D from diameter 6.2 to diameter 5.6, making the answers 44.9 and 49.5. This is actually the result shown in the PDF attached in the original post.
pylfrm
RE: Datum Shift
This is what happens if someone (me in this case) does not double-check his reply and numbers before posting it. And this is how instead of clarifying things more mess can be done.
So I will just re-post my long comment with modifications in red. Hopefully this time with no error:
-----------
Perhaps it is just my impression, but I have a feeling that a clarification is needed here. This will be about the second stack (the one attached to the OP).
First, the key input for the discussion is pylfrm's post from 25 May. Up to that point I had been too focused on trying to explain to aniiben the difficulties/limitations of VC/RC approach in stack-up calculations that I simply missed one very important thing - the counterbores in question are positioned individually to D(M), not to A|D(M), which in consequence means that the calculations shown in the workbook are... how to put it... wrong. One thing is that the datum feature shift values in rows D and P shall not be 0.4, but 0.1 instead. And additionally, even with the values in rows D and P corrected, we would have to make a bunch of assumptions about perfect orientation of considered features relative to each other, which is not what we are told to do. To be able to calculate Xmin and Xmax correctly (without a need of making any assumptions), we would have to know the flange thickness and would have go into trygonometry - this is what I tried to explain in my post from 26 May.
Also, assumptions would not have to be made, in my opinion, if the positional callout for counterbores was referencing |A|D(M)|. In that case correct answers would be Xmin = 44.9 and Xmax = 49.5, as shown in the book.
------
Then some follow up questions were thrown in, which essentially have been also answered by pylfrm:
1. What would happen if '4X INDIVIDUALLY' and '4 PLACES INDIVIDUALLY' notes were removed (aniiben)?
Then the position callout for counterbores would be treated as simultaneous requirement meaning that no datum feature D shift would be included in the calculations (line D and P from the original stack would be 0). Additionally, since the stack would not need to include position tolerance of thru holes D relative to datum axis B, unlike in the original stack, lines F, G, H, J, K, L would go away. That would result in Xmin = 46.5 and Xmax = 47.9.
2. How will the stackup will change if datum feature D is called RMB (greenimi)?
If the question is about modification of the original stack, not modification of aniiben's modification, datum feature shift values in lines D and P in the original stack shall be 0. This gives Xmin = 45.7 and Xmax = 48.7. Again, these values are true if assumptions about perfect orientation of all considered features relative to each other are made.
If the question is about modification of aniiben's modification, the answer is Xmin = 46.5 and Xmax = 47.9. So this actually means that it does not really matter what material boundary condition (MMB, LMB or RMB) the datum pattern D is referenced at in the positional callout for counterbores - Xmax and Xmin values stay unchanged. It is because the stack is calculated between features that are gaged simultaneously in both cases.
3. And finally, aniiben's question about missing things in his/her calculations/thought process that result in Xmin = 45.7 and Xmax = 48.7.
The difference of 0.2 in both cases comparing to pylfrm's answer comes from the fact that you did not include two radial datum feature D shifts of 0.1 that are possible if both individual thru holes are made at LMC [0.1 = (6.4-6.2)/2].
RE: Datum Shift
RE: Datum Shift
I do not know to work with VSA, but do you think this software is capable to do this kind of calculations (min / max calculations for individual features on the same part)?
I read that VSA is good to work with individual assemblies (multiple solidmodels loaded) and no so much with individual parts (relationship within the features on the same part). If you have experience with VSA could you please offer some insights? I am trying to learn more.
Also, in my opinion, if this kind of simple arrangements ---(and I agree with you: there are simple in the complexity of the entire assembly, probably, as shown by the OP ---both examples) are not properly understood (and I do not claim I do it) then the VSA will be a good and expensive number generator. Sometimes they make (those softwares) worthless sheet of paper.
More or less as the CMM it is. If the values on the CMM report are not understood to a certain level, then are just that: numbers.
RE: Datum Shift
One of the outputs of VSA is the solution method, which is the actual program it runs to do the simulations, so it's not just numbers. Just look at the sequence of transforms to see how the final results are arrived at.
Cookbook calculations don't do so much for understanding. They are shortcuts developed to solve particular sorts of problems and often require simplifying assumptions, such a perfect orientation, to do what they do. They also don't handle the distribution of variations that production parts will experience, and therefore are useless for predicting production yields.
What does help understanding is to draw parts that have features with compliant but extreme variations and see what combinations make for worst cases and to look at controls that limit those variations. If a person understands the qualitative effects of allowable tolerances, then the rest can be worked out.
RE: Datum Shift
A star for you, pylfrm. Great job!
RE: Datum Shift
I notice the following bullet point on the VSA product overview:
Seems rather optimistic considering the slow progress with STEP AP242 and such, but perhaps I'm out of the loop. When you used VSA, were you able to import tolerancing with the CAD models, or did it have to be entered manually after importing geometry?
Also, any idea about the cost?
pmarc,
Thanks.
pylfrm
RE: Datum Shift
John-Paul Belanger
Certified Sr. GD&T Professional
Geometric Learning Systems
RE: Datum Shift
I expect it still costs a lot more than people like, because why not? It's only bought by those who can see some value in good control of their product variation and it seems like few have that desire**. The version I used was about $10k for the seat and a few grand for the annual maintenance, but that was directly from VSA Inc, long before Seimens bought it along with UG. PTC stuck with the less flexible Ti-Tol/Raytheon/whatever originating from ADCATS and that was that. Unlike most tolerance analysis software, because VSA generated intermediate C code, one could add in any conceivable module that was dimensionally dependent. Suppose one modeled combustion efficiency based on all the variations in chamber geometry, one could look at variations based on cylinder diameter or con-rod length. Likewise, if there was some other interdependency not readily represented by dims and FCFs, that could be accounted for as well.
JP - that's why I suggest skipping plug-and-chug in favor of creating images of variations. It's not possible to be sure the formula is right when the user has no idea what the part will be like. I have found it much better to learn how to derive the equations from the observable variations than to memorize special cases and their list of assumption.
** I have seen no evidence that anyone but big auto makers are interested. Perhaps no one else wants to walk as close to the manufacturing capability over so many parts in order to save manufacturing expense. Everyone I've been exposed to will slot holes and shoot for the nominal and hope for the best. They don't gather much data from manufacturing processes to use for yield predictions. The last place I worked the parts coming in didn't match the drawings, but it was OK as long as they fit in production. There had been e-mails about changes and the company never got around to updating their own docs, though the supplier updated their process. This is a company subject to FDA oversight. Their QA didn't notice because they only check on complaints and the first articles when they are included on the change notice.
Still it's not magic. Early on, one of the manufacturing engineers asked about analyzing a weldment for warping due to welding. I noted that the weldment was done without a fixture, the process called for a variable number of passes and the parts on the drawing didn't nominally fit but were sized to let the welder grind them to fit. But sure, a great candidate for a geometric tolerance analysis. Later on I got a manufacturing demand for a drawing change to allow more variation and to change all the welds from skip welds to continuous because "That's what the welders are doing." Can't have non-compliant parts if the drawing is changed on every production run to account for what manufacturing changed. If I say we really paid the piper, it would be an in-joke.
RE: Datum Shift
pmarc,
Just a small caveat to your above statement:
See the same book, page 12-14 -example 5. One hole to A, C, D(MMC) and the other A, C and B.
VC and RC still works.
Ø 8.2-8.6 pos Ø.016 (MMC), A, C and D(MMC/ MMB)
VC: 8.04, RC: 9.16
Ø4.0-4.4 pos Ø 0.1 (MMC), A, C and B
VC: 3.9, RC: 4.9
16 basic dimension between the holes. (Calculate the max and min dustance between the edges of Ø 8.2-8.6 and the Ø 4.0-4.4)
I guess we can call it two different datum systems/ two different setups or coordinate systems.
VC and RC approach still works. Am I correct?
RE: Datum Shift
I did not check each and every line of the stack you referred to, but to answer your question, the VC/RC approach will work in this case because change of tertiary datum feature references [B vs. D(M)] have no influence on what happens in vertical direction - the direction of the stack.
In other words, what makes VC/RC approach usable in this very scenario is the fact that both holes are positionally controlled relative to the same primary and secondary datum features A and C, and that the diffence in tertiary datum features has no influence on calculated distance.
If, however, the stack objective was to calculate the distance between the edge of the big hole in the center and the edge of dia. 8.2-8.6 hole, then the VC/RC approach would not work (at least not that easily).
RE: Datum Shift
Is it safe to assume that VC/RC approach works on a limited bases only?
Personally, I like VC/RC, but looks like I cannot use it “all the time”
Also, for the “Kurlikovaski method” ---see first embedded graphic (not the attached one) exercise 12.4 page 12-23 from the book --- am I correct in saying that the perpendicularity error on datum feature B was not included in the stack for the X minimum because the author intended to include the datum shift ?
The natural question (s) for the experts is when you include one (perpendicularity) versus the other (datum shift) as is obvious we cannot include both?
RE: Datum Shift
1. Yes, I think you could say that VC/RC approach (without any tricky workarounds) works on a limited basis only.
2. The perpendicularity error on datum feature B is not directly shown in the stack, but it is included in the datum feature B shift calculations (see bonus/datum shift chart in the book).
3. Yes, I would say you cannot include both in the stack.
RE: Datum Shift
Do you agree also with my assessments on the VC and RC thread?
We used, for the sake of comparation, your "min wall" thread calculations where the form error on the datum feature must be taken in consideration to get the correct min wall values.
I made a statement there that IF the datum feature is at RFS then the form error should be included separately versus IF the datum feature is at MMB or LMB than the form error is already included/ or does not need to be included.
http://www.eng-tips.com/viewthread.cfm?qid=425923