×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

When to conduct pile load test

When to conduct pile load test

When to conduct pile load test

(OP)
Hi,

After pile driven into soil, when is the appropriate time to conduct the pile load test (maintained load test & pda test)

1. Is the resting period for skin friction and end bearing pile is different? I read that some suggesting straight away, some said 3 days, 2 weeks and even 1 month.

2. Will different type of soil affect the time for testing?

3. What about the bored pile?

Thank you

RE: When to conduct pile load test

General rule: for silts and clays, the longer the wait, the higher the static capacities (full-scale load test). For mostly sandy profiles, 1 to 2 days.
Practically, the sooner the better, so pile production can start.
For auger cast piles, we never waited more than 1 week.
If the contractor is pushing for a shorter wait time between installation and test, the test results will be conservative (everyone wins unless the test results are lower than expected).

RE: When to conduct pile load test

For PDA tests on large project we usually do some tests at the end of initial drive and some after a week or two to determine the amount of setup (or relaxation).

I have seen piles with fairly substantial relaxation so you should be cautious about assuming that the longer you wait the higher the capacity will be as this is not always true.

RE: When to conduct pile load test

My experience was minimum one week to allow the soil thixotropy, releasing the excess pore water pressure and soil dilatation.
The bored pile will be depending on the concrete strength to hold the maximum load.

RE: When to conduct pile load test

geotechguy1:
In what soil profiles do you see substantial relaxation beyond 7 days?
Is this demonstrated by full scale pile load tests, or just PDA, or both?

RE: When to conduct pile load test

Driving piles in very dense silty sand. The mechanism is supposedly negative pore water pressure generated during driving. Demonstrated by PDA tests in some cases, in others simple observation - the pile reaches practical refusal at the maximum allowable energy, but is able to be re-driven a day later.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources