INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Connections Calculation

Connections Calculation

Connections Calculation

(OP)
Hi guys,

I have this situation where I was hired to prepare shop drawings for a steel framing..There were some connections shown on structural drawings, like moment connections, but some connections were missing..so I came up with some connections details that seemed the most reasonable for me..after the drawings' first submission, EoR had a lot of comments which were addressed and connections details seem to be approved as noted but he wants to see calculations now..And my question is if this is how it is supposed to be done..? When I am FoR I calculate the whole structure and I show all the details,including connections (which I think are the most important elements in any steel structures..) If any connections are missing, contractor's detailer asks for those details and I provide them..EoR should claim the responsibility for his design...I don't mind preparing calculations for him but he should give me forces in nodes right? What would be your approach here? I will appreciate any advice.

RE: Connections Calculation

In some states, even though connections are delegated design, the EOR is still liable.

I do not know all of the details, I am sure there are some grey areas. I am also sure others will be able to provide a more thorough answer.

RE: Connections Calculation

It depends on the contract documents. AISC 303, Code of Standard Practice for Steel Buildings and Bridges, has three options for connections. See section 3.1.1. If the fabricator designs the connections, the EOR needs to provide the loads. If the fabricator is not responsible for the connection design or selection, the EOR should provide the missing connection information/details.

RE: Connections Calculation

(OP)
Thank you very much !

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources