INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Glycol Reboiler Vessel + Glycol Reboiler Bundles to get complete U stamp

Glycol Reboiler Vessel + Glycol Reboiler Bundles to get complete U stamp

Glycol Reboiler Vessel + Glycol Reboiler Bundles to get complete U stamp

(OP)
Dear Sir/Mdm,

I'm having an issue here to complete and fulfill client requirement.

Situation

1. I've 2 equipments with 2 tag no and 2 datasheets
2. One equipment is fabricate in Oman (register as vessel) and another one fabricate in Malaysia (heater bundles; tube side only)
3. Fabricator in Malaysia has performed HT in the tube side & shell side (using dummy vessels).
4. Fabricator in Oman has retrieve the full u-stamp as a vessel but fabricator in malaysia only got U-part stamp for tube only (from AI).
5. Now, when we integrate this 2 equipment together (through the flange) in the process, glycol reboiler vessel is U-stamp and tube bundle is U-part, client has refuse it to accept it as U-part. They want it as full U-stamp eventhough it just tube bundle only (without the shell, as the shell is fabricate in Oman).

The questions is, what should I do to get this glycol reboiler bundles (tube only) as full U-stamp?

RE: Glycol Reboiler Vessel + Glycol Reboiler Bundles to get complete U stamp

Only the fabricator of the tube bundle can do it. If it was tested external/internal it can be done by ammending the ASME, National Board Registered Dada Report, all with the concurrence of the A.I.
Next time you can arrange the vessel fab. To take responsibility and stamp the whole vessel by getting a partial from the bundle mfr. But I guess the can not be done at this time. But only if the Vessel mfr AI will sign off as a complete HX.

General Blr. CA,USA

RE: Glycol Reboiler Vessel + Glycol Reboiler Bundles to get complete U stamp

I suggest you contact the AIA's involved for guidance to reconcile the issue.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources