How to determine industrial user natural gas design load (Coincidence factor)
How to determine industrial user natural gas design load (Coincidence factor)
(OP)
Designing Natural gas industrial users metering and regulating station, for years I have been using a rule I found in a Dresser meter brochure to determine the industrial design load. This rule considers a coincidence factor that decreases with the number of connected equipment. See below
Qty of consumption equipment Factor (multiply by)
0-5 ------------------------------------------------ 1
6 ------------------------------------------------ 0.9
7 ------------------------------------------------ 0.85
8 ------------------------------------------------ 0.83
Does anybody know of technical papers that have best practices, some of the engineers want to use 100% of the connected load to design the stations and I want to have a source other than the brochure to discuss the point to define a general practice.
Thank you
Qty of consumption equipment Factor (multiply by)
0-5 ------------------------------------------------ 1
6 ------------------------------------------------ 0.9
7 ------------------------------------------------ 0.85
8 ------------------------------------------------ 0.83
Does anybody know of technical papers that have best practices, some of the engineers want to use 100% of the connected load to design the stations and I want to have a source other than the brochure to discuss the point to define a general practice.
Thank you