Bored Piling
Bored Piling
(OP)
If the pile toe levels has been exceeded by more than 500mm or so, what is the best rectification for this:
I have thought about a few options but advise would be great:
* pour in concrete to the toe level
* do nothing as the desirable toe level has been passed and therefore has met the piling requirement.
Any ideas would be greatly appreciated.
Thanks
AKE
I have thought about a few options but advise would be great:
* pour in concrete to the toe level
* do nothing as the desirable toe level has been passed and therefore has met the piling requirement.
Any ideas would be greatly appreciated.
Thanks
AKE





RE: Bored Piling
RE: Bored Piling
I have a set of drawings which shows the toe levels. It has already been determined during the design phase which included geotech assessments.
So my question is that during actual construction what happens if the toe level has been exceeded? Is this an actual issue or can that be rectified?
Thanks
ake
RE: Bored Piling
RE: Bored Piling