INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Brick Veneer above last wall anchor?

Brick Veneer above last wall anchor?

Brick Veneer above last wall anchor?

(OP)
Hello,

I am designing a metal stud wall with brick veneer on the face of the first floor, on one edge of the building, resting on the slab. The stud system sits outside of the building and is attached back with clips, so the first floor studs are attached to the underside of the second floor studs (via. deflection head track) which are cantilevering off of the second floor slab. The height of the studs are set and cannot be adjusted to allow for drift between floors.

The issue I'm having is this, the brick veneer extends 3 bricks above the deflection head track. We cannot tie the brick into the second floor studs as any differential movement between the floors will cause the bricks to shear. Is it okay to leave rows of brick floating like that? ACI 530 has anchor spacing requirements but nothing about if an anchor is required in the final brick row or not, and I've seen plenty of details online that look like they don't fasten the very top row of bricks. We would be specifically calling out that they place the final top anchor in the brick row closest to the top of the first floor studs, thus leaving only ~5 inches of brick above the final anchor (Well under half the maximum vertical spacing allowed, 18in/2 = 9in)

Thanks.

RE: Brick Veneer above last wall anchor?

Why not run the studs continuous to the top of parapet and tie back to the slab edges with deflection clips? That would seem to eliminate the issue.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources