INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Butt-weld joint preparation

Butt-weld joint preparation

Butt-weld joint preparation

(OP)
According to ASME VIII Div.I, are there particular restrinction of type of butt-weld joint preparation (X or Y, ando also angle 30° or 45°)? I found only in UW-9(b) that "the dimensions and shape of the edges to be joined shall be such as to permit complete fusion and complete joint penetrarion". Do you know other references? Or in these cases the guideline is "designed by experience"? tnks

RE: Butt-weld joint preparation

ASME VIII does not require absolute joint geometry designs as you have found in the referenced UW-9.

RE: Butt-weld joint preparation

Hi ElCId,

It's a good question especially because ASME VIII is a design standard. Although there are strength requirements for joints but some guidelines on joint configuration would be also nice.

RE: Butt-weld joint preparation

Hi ElCId,

type of butt-weld joint preparation is basic welding / fabrication knowledge had therefore no place on the Code.

Have you ever read the Code? On the Foreword of each Code Section is clear stated:
"The Code does not address all aspects of these activities and those aspects that are not specifically addressed should not be considered prohibited. The Code is not a handbook and cannot replace education, experience, and the use of engineering judgment. The phrase engineering judgement refers to technical judgments made by knowledgeable engineers experienced in the application of the Code."

Regards - Juergen

RE: Butt-weld joint preparation


According to Sec-IX,QW-401.4 Nonessential Variable (Procedure). A change in a welding condition which will not affect the mechanical properties of a weldment (such as joint design, method of back gouging or cleaning, etc.This is the guideline for conventional arc welding processes.Though for non conventional process.g FSW, Laser Welding there are some imposed restrictions.

Joint design(with included angle) used to be restriction imposed by European codes but not by ASME. Having said that the designer has to suggest the best groove for quality and productivity. In a large fabrication organization welding engineer is the additional resource for the same as he or she executes the work on the shop floor.

Thanks.

Pradip Goswami,P.Eng.IWE
Welding & Metallurgical Specialist
Ontario,Canada.
ca.linkedin.com/pub/pradip-goswami/5/985/299

RE: Butt-weld joint preparation

kudos to Pradip for directing to ASME B&PV Code Section IX. This is the text that will address rules for joint configuration, welding, etc.

RE: Butt-weld joint preparation

Thank You Tom.
ASME is flexible on this aspect.However the fabricator needs to prove the joint/weldment integrity at the end.For critical joints (saw Narrow GAP SAW/GMAW)in addition to a qualified PQR, shop/ weld mock up coupon may be specified as required.

Pradip Goswami,P.Eng.IWE
Welding & Metallurgical Specialist
Ontario,Canada.
ca.linkedin.com/pub/pradip-goswami/5/985/299

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources