INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Discontinuous Sheathing at Rimboard

Discontinuous Sheathing at Rimboard

Discontinuous Sheathing at Rimboard

(OP)
I've never had this specific request before so I thought I would put it out on the board to see what other opinions were:

The residence uses 14" deep I-Joists with 9'-1" stud walls. The designer/contractor does not want to have to install any mid-span blocking for panel splices (sheathing). They intend to use 4'x10' OSB sheathing, applied vertically. However if the sheathing is held to the top plate it ends at about midway on the 14" x 1-1/4" rim board. My typical detail does not allow for any splices in this region (I think the idea was to provide continuity/redundancy over the rimboard, bottom plate and lower half of the studs when I originally created it). Their idea is to then cut a small strip of sheathing to cover this bottom half of the rimboard. Provided they can get about 5" to 6" of sheathing lapping the rimboard I don't think I see a specific problem but I do need to give this some more thought.

A confused student is a good student.
Nathaniel P. Wilkerson, PE
www.medeek.com

RE: Discontinuous Sheathing at Rimboard

It would be more like 10" lapping the rimboard if my math is correct. That would be fine by me, provided you aren't relying on the sheathing fastening directly to the nailer on the top of the foundation wall. And even then, I could likely be persuaded.

RE: Discontinuous Sheathing at Rimboard

what is the concern? appropriate shear transfer in wind/seismic?

you could double up or block the rim joist and nail through the top/bottom plates to connect the wall to the diaghram.

for overturning and some shear, you could use simpson MST straps to bridge the walls across the floor plate.

If you are still trying to use the sheathing to transfer into the rim joist, you could insist they use plywood. much better performance than OSB.

RE: Discontinuous Sheathing at Rimboard

X3 for this not being a deal breaker. Obviously, where you need to transfer tension across the plenum, you'll need to do it some other way. As an example, modular built homes often lack the sheathing continuity described above. Also as an example, the same modular built home fly apart like Lego during hurricanes in the absence of a bunch of shiny connection hardware.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.

RE: Discontinuous Sheathing at Rimboard

Quote (KootK)

As an example, modular built homes often lack the sheathing continuity described above
Most homes lack this (at least in our area)

RE: Discontinuous Sheathing at Rimboard

Mine too.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources