INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Codemaster MWFRS and C&C Procedure

Codemaster MWFRS and C&C Procedure

Codemaster MWFRS and C&C Procedure

(OP)
Hello Everyone,

I have a copy of Codemaster Wind Design Overview ASCE-10 and I'm a little confused about the design procedure for my building. I have a partially enclosed building and a height less than 60'. I would like to use method 1 (Chapter 27, Part 1) Directional Procedure for buildings of all heights for my MWFRS calculation. But when I go to step 8 (C&C) I need to use chapter 30, part 1 (h < 60 ft)and it says that the counterpart to envelope procedure is chapter 28, part 1 for MWFRS.

So, my question is, can I still use Chapter 30, part 1 for C&C and also use Chapter 27, part 1 for MWFRS or do I need to use Chapter 30 part 1 with Chapter 28, part 1. Obviously, I want to use chapter 27 part 1 since it's easier, I'm just wondering if I can interchange modes.

Thank you very much.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.