INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

simulated post-weld heat treatment (SPWHT)

simulated post-weld heat treatment (SPWHT)

simulated post-weld heat treatment (SPWHT)

(OP)
Please share your thoughts herein,
How is SPWHT done? ٌWhat is the exact need for SPWHT at plate mill?

RE: simulated post-weld heat treatment (SPWHT)

This test is to done at the mill, during production & heat treatment of plates/forgings(base metals) prior to dispatch. Under the present steel making scenario and knowledge base one may not have to ask this for all types of materials. However if the design Code is Sec VIII, DIV-2, and design requirements are very stringent and for critical operations, then vendors have this flexibility to ask for this requirement for overall integrity of the fabricated component . The intention is to evaluate the mechanical properties (tensile & charpy impact especially) conforming to the special/additional heat treatment requirement and meeting the design code/project specifications' requirements..

For example: Say materials is Cr-Mo-V steel PWHT envisaged as the design code is 4 hrs. Fabricator foresees the problems,and anticipates that there would at least one or 2 Full fledged repair cycle even after PWHT. So with additional 2 cycles(8 hrs) of PWHT what should be the mechanical properties? One may ask those information from the mill to be verified prior to delivery.

However it comes with a cost and may delay the delivery.

Requirements are specified in ASME Sec-II,Part-A,,SA-20, Supplementary Clause S3



Thanks.

Pradip Goswami,P.Eng.IWE
Welding & Metallurgical Specialist
Ontario,Canada.
ca.linkedin.com/pub/pradip-goswami/5/985/299
All provided answer are personal opinions or personal judgements only. It's not connected with any employers by any means.

RE: simulated post-weld heat treatment (SPWHT)

(OP)
pradipgoswami What will force us to ask for it? Having PWHT in our manufacturing process or impact test or ...? If we have 1 cycle PWHT would it be needed to be asked for?

RE: simulated post-weld heat treatment (SPWHT)

Pradipgoswami,

SPWHT is required in the scope of ASME VIII/1 and VIII/2 – see HEAT TREATMENT OF TEST SPECIMENS (UCS-85 and 3.10.2).

Regards - Juergen

RE: simulated post-weld heat treatment (SPWHT)

Requirements for simulation test coupon are driven by the following requirements:-

-Design and Construction Code
-Any additional design conditions imposed, client/project specifications
-Materials of Construction, and thickness(thicker materials may have anistropy and simulation HT is generally called for to safeguard the integrity of the products)
-Design Temperature Envelope(i.e the design temperature of the components being fabricated.

Could you please elaborate the above requirements.

Thanks

Pradip Goswami,P.Eng.IWE
Welding & Metallurgical Specialist
Ontario,Canada.
ca.linkedin.com/pub/pradip-goswami/5/985/299
All provided answer are personal opinions or personal judgements only. It's not connected with any employers by any means.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources