INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Analysis of segmental bridge built by balanced cantilever method

Analysis of segmental bridge built by balanced cantilever method

Analysis of segmental bridge built by balanced cantilever method

(OP)
Hello bridge guys,

I'm going to assess a 20 years old post tensioned bridge of which the concrete deck was cast in-situ with travelling gantry attached to cantilever ends.

My question is, after 20 years have gone, is the creep induced by the weight of the gantry still "significant"? I mean is it still necessary to consider the weight of gantry in estimating the creep effect?

Thanks,

J

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources