INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Guidance on interruption of a continuous pour?

Guidance on interruption of a continuous pour?

Guidance on interruption of a continuous pour?

(OP)
Our contractor was performing a continuous pour for a wind turbine foundation. They interrupted the pour for 45min before continuing. Is this acceptable or does any ACI (or other provider) offer guidance on determining if this interruption is acceptable? Maybe these is some form of testing that can be performed to insure the joint is acceptable.

RE: Guidance on interruption of a continuous pour?

Is the joist accessible/visible from a surface? Or is it length-wise inside the pour?

Professional and Structural Engineer (ME, NH, MA)
American Concrete Industries
www.americanconcrete.com

RE: Guidance on interruption of a continuous pour?

What was the temperature? and were there any admixtures in the concrete? How much had they poured and how much did they have left? I can only speak from experience as I haven't dug too much into ACI (CSA for me). I would first get a feel for how cured I estimate the concrete was at the time they resumed pour. Nice thing about concrete is that if they created a cold joint, you would almost certainly see it when they strip it and you are inspecting for release for backfill. I do remember there is standard practice for what percent cured (in strength) one batch is no longer considered monolithic. I guess this is what you are looking for.

RE: Guidance on interruption of a continuous pour?

Looked around a bit but there's not much in term of chart. Portland Cement Association says if the concrete was still plastic then there is no cold joint. If you calculate that you may have a cold joint, try to make yourself, or an inspector available when they strip so you can see if there is a cold joint. Contractors sometimes try to hide the imperfection so better not to give them the chance to see the cold joint first.

RE: Guidance on interruption of a continuous pour?

Do you have continuous rebar, top & bottom, going thru the joint? Please confirm.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources