INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Adjacent Footings & 2:1 Slope

Adjacent Footings & 2:1 Slope

Adjacent Footings & 2:1 Slope

(OP)
For the past 20 years, i've enforced a 2:1 soil slope requirement for adjacent footings, but, i cannot find any current code documentation to verify this. I'm in Wisconsin which is currently under IBC 2009.

I've been looking for code documentation, on and off throughout the years as i am confronted with this every other month, but, i have not found it. Fortunately, i've been dealing with contractors who accept my, apparently reasonable enough explanations, so i haven't been forced to locate an exact reference. However, i need to find this reference for good practice.

I BELIEVE the origin of this specification came either from earlier codes or OSHA, but, i'm not coming up with anything.

Is this IBC, OSHA, ASCE or other?

Does anyone have a reference to this?

Thank you!

RE: Adjacent Footings & 2:1 Slope

In my neck of the woods, the slope is specified in the geotechincal report, or should be. That said, I've never seen anything shallower than 2:1 or steeper than 1:1 in non-rock strata. 10:7 seems popular out east but they tend to have better material.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.

RE: Adjacent Footings & 2:1 Slope

OSHA 1926.652 has the requirements for sloping and trenching for excavations during construction. It allows slightly steeper slopes that 2:1, see Table B-1 in Appendix B.

Go Bucks!

RE: Adjacent Footings & 2:1 Slope

Depends on the soil. The geotech should give you guidance. 2:1 is conservative.

When I am working on a problem, I never think about beauty but when I have finished, if the solution is not beautiful, I know it is wrong.

-R. Buckminster Fuller

RE: Adjacent Footings & 2:1 Slope

(OP)
According to OSHA Table B-1 (that straub46 directed me to), the shallowest required slope is 1.5:1 or 34 degrees, which is closely equivalent to KootK's 10:7.

RE: Adjacent Footings & 2:1 Slope

Look out, because regardless of the grade of the slope, building close to the edge can effect your bearing capacity. You end up losing confinement against bearing failure on the slope side.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources