×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Two Way Slab Additional Reinforcement Call-Outs

Two Way Slab Additional Reinforcement Call-Outs

Two Way Slab Additional Reinforcement Call-Outs

(OP)
Hey,

I'm trying to get people's opinions on the proper way to call out additional reinforcement required for a two-way slab.

I've seen where its just called out as (11) #7 T (11 #7 bars at the top). The instance would be additional rebar over a column.

But should the EOR show how long these bars are, and at what spacing?

If the EOR doesn't, how does the steel detailer know? Just based on embedment length? The spacing?

Thanks

RE: Two Way Slab Additional Reinforcement Call-Outs

Two versions that I see commonly:

OLD SCHOOL

- Use column strip / middle strip conventions in plan with typical details showing the disposition of rebar.

- Fabricator figures out the lengths of most bars using typ details.

- Good for simple, regular slabs and column layouts. Painful for complex stuff. I may post a terrible example of this later today if I have time.

- KootK wants this method to die.

MODERN METHOD

- Call out a continuous bottom mat of steel everywhere. Size and spacing.

- Add some additional bottom steel in plan where needed at specific locations. Specify length and spacing.

- Call out the column top steel either explicitly on plan (length, size, spacing) or define column "mats" elsewhere if the plan gets too busy.

- Add additional top steel where required, calling up size length and spacing.

- Cover a few simple conditions with typical details.

- This method is easier to construct, results in a zillion percent less queries, reduces shop drawing review time, and reduces field review time. It even makes for prettier drawings in most cases in my opinion.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.

RE: Two Way Slab Additional Reinforcement Call-Outs

(OP)
To follow up, do you guys typically have a top bar plan, and a bottom bar plan?

RE: Two Way Slab Additional Reinforcement Call-Outs

Only if the system is so complex that becomes a necessity. That's part of the beauty of the continuous bottom mat approach. 90% of the bottom steel layout is communicated with a couple of plan notes smaller than my thumb.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.

RE: Two Way Slab Additional Reinforcement Call-Outs

(OP)
And just out of curiosity, what program do you use to design the slab? I'm using RAM Concept, developing a love/hate relationship...

RE: Two Way Slab Additional Reinforcement Call-Outs

I usually have bar designations (top and bottom) on plan and in my schedule I call out the length and the placement of it. For additional top reinforcement, sometimes I call it out on plan, if it will fit, but usually I just add it to the schedule.

RE: Two Way Slab Additional Reinforcement Call-Outs

Mostly SAFE these days. A little bit of PCA slab for easy stuff. Other than licensing issues, Concept is hands down my favorite. I believe it to the be the fastest production tool for slab design by a significant margin. It's just so much easier to draw stuff than with other packages.

Below I've added the following:

1) Standard detail/plan that is often used for the middle strip / column strip detailing method.
2) An irregular plan where, in my opinion, the arrangement becomes almost incomprehensible.


I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.

RE: Two Way Slab Additional Reinforcement Call-Outs

We do a bottom mat with add bars 3B5, etc. For the top mat, we call out the top bars 10T6, etc. For lengths, we reference the ACI standard detail and have the detailer do them. It is quicker in design but it takes longer during the shop phase since we have to check all the lengths and they typically need adjustment.

If I had the time and the fee, I'd call out the lengths of each bar.

We do one plan for rebar and one plan for details / geometry. Both top and bottom bars are on one plan.

When I am working on a problem, I never think about beauty but when I have finished, if the solution is not beautiful, I know it is wrong.

-R. Buckminster Fuller

RE: Two Way Slab Additional Reinforcement Call-Outs

I have absolutely no idea what's happening in KootK's drawing.

RE: Two Way Slab Additional Reinforcement Call-Outs

We often have four plans for each level in complex buildings with lots of setdowns, etc. Profile plan, bottom steel plan, top steel plan, post-tensioning.

RE: Two Way Slab Additional Reinforcement Call-Outs

Don't leave it up the scheduler to guess how you want to arrange your splices, bar shapes etc. When in doubt, draw it out!

For RC slabs, I'll draw a typical top and bottom mat and then call up additional bars where needed. I would definitely have separate top and bottom reo plans though...

RE: Two Way Slab Additional Reinforcement Call-Outs

Quote (TLHS)

I have absolutely no idea what's happening in KootK's drawing.

For the benefit of future generations reading this thread, that is most definitely not "KootK's" drawing. It is an example of a presentation style that KootK would like erased from human kind's collective memory.

Quote (Trenno)

I'll draw a typical top and bottom mat

How do you handle that with the top mat? A continuous top mat is a rare thing and it's an equally rare building that's regular enough to have a single column top mat be applicable.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources