INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

PWHT for Branch connection weld

PWHT for Branch connection weld

PWHT for Branch connection weld

(OP)
Hello everybody

as subject, I have many joints Olet (weldolet/Nipoflange) are seft reinforement more than 25mm welded to pipe run 10''SCH80(15.09mm) & 12"SCH80(17.48). As per ASME B31.3 2014 defined that Tm+Tc>25mm in FIG.328.5.4F is need to PWHT or preheat 95deg without PWHT. but currently we are used WPS qualified by PWHT.

my question: Do we need to perform PWHT in case?

RE: PWHT for Branch connection weld

quatle,
If your welding procedure is as per ASME IX you must PWHT or qualify a new PQR/WPS without PWHT,
Regards,
DD

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources