INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

LL for Pool Deck

LL for Pool Deck

LL for Pool Deck

(OP)
I am trying to figure out what to use for a LL of a pool deck. The pool is located in a municipal facility with access to the general public. I need to design some shoring for the suspended concrete deck around the pool (at the same elevation as the top of the pool) as the concrete is beginning to spall. The intention is for the shoring to be temporary until they renovate the facility in two years.

I'm thinking 100psf as that is what is used for the public areas of a hotel.

RE: LL for Pool Deck

I don't recall the actual numbers for "live load" but in a public-access, public-playing-and-dancing-while-drunk-and-crowded area like a pool deck, I'd plan for the heaviest possible "stupid load" you can think of.

Then remember most drunks are already more stupid than that.

RE: LL for Pool Deck

100psf should probably be adequate. If you reference ASCE 7-10 they recommend 1.5x the occupancy served not required to exceed 100psf for balconies and decks in table 4-1. If you want a little more comfort you can increase the live load but I think you should be okay in terms of justifying it to meet code compliance designing for 100psf. And for the comment above dance halls are designed for 100psf I believe so should be good for that : ). Have to get ASCE to add a drunk increase factor next code update lol

RE: LL for Pool Deck

I have used 100psf. If you look at the most common usage I believe it to be conservative. Consider the end of a pool deck that is 40'x10'. This would equate to 40,000lb of live load or 228 people if they averaged 175lb. Each person would have 1.75sqft of space. That is not a lot of space to stand when people want to be comfortable.

RE: LL for Pool Deck


I agree with the 100 PSF live load. It is a common recommendation for public spaces.

Ralph
Structures Consulting
Northeast USA

RE: LL for Pool Deck

Are there any short-term concentrated loads anticipated (or envisioned) which could locally exceed the results from the 100psf load approach?
Dave

Thaidavid

RE: LL for Pool Deck

How about an occasional repair truck?

RE: LL for Pool Deck

I would design a lot higher, maybe 250psf. You stated "intention is to be temporary---- renovated in 2 years", which to me means 'we will fix it on your dollar when it collapses in 15 years'. If they can afford to do the supports, the only thing left to do is to demo the existing, add the proper steel and place new concrete.

Richard A. Cornelius, P.E.
WWW.amlinereast.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources