Microsoft Project 2000 - Days not translating correctly!!
Microsoft Project 2000 - Days not translating correctly!!
(OP)
I just starting using Microsoft Project 2000, I have a project plan and need to include baseline hours, estimated hours, and actual hours on a project. Is there a way to do all of this and still only calculate the actual number of hours worked?
I entered all of my information into Project and placed a new column called "work" for hours worked so far. When I place a number of hours worked, The number of days is not translating correctly. The days are staying at 1 day. Does anyone know how to fix my number of days?
I entered all of my information into Project and placed a new column called "work" for hours worked so far. When I place a number of hours worked, The number of days is not translating correctly. The days are staying at 1 day. Does anyone know how to fix my number of days?





RE: Microsoft Project 2000 - Days not translating correctly!!
RE: Microsoft Project 2000 - Days not translating correctly!!
If you pick any column and right-click, the context menu includes insert column. The dialog box that comes up has the first entry of "Field Name". If you select the pulldown list, and scroll to the top, you'll find entries for Actual Start, Actual Work, % Complete, % Work Complete, etc.
TTFN
RE: Microsoft Project 2000 - Days not translating correctly!!
One more question, I added three columns:
1.) work
2.) actual work
3.) remaining work
When I place the actual hours worked, Project rounds the numbers. For instance I place 262 actual hours and when I go to the next line, Project takes the 262 and changes it to 262.08. Is there a way to make Project except only what I place in the actual work column so that the remaining hours is correct? Any help is greatly appreciated.
RE: Microsoft Project 2000 - Days not translating correctly!!
Usually, if you allocate resources, Project will calculate the duration for you.
TTFN