Slab on Grade Relief Port Locations
Slab on Grade Relief Port Locations
(OP)
I've got a slab on grade that may see some water coming up from the bottom at some point in the future. Rather than tank the basement, we'll have these nifty relief ports installed in the slab on grade. My questions:
1) How should I space these things?
2) Are there certain locations that are better than others? I've been assuming that near bu not at floor drains (low points) would be good. And I'm drying to keep them out of the drive isles for durability.
Anyhow, I'll take whatever recommendations anyone cares to offer. I've run this by both my mechanical and geotechnial consultants and the responses so far have been less that inspiring.
1) How should I space these things?
2) Are there certain locations that are better than others? I've been assuming that near bu not at floor drains (low points) would be good. And I'm drying to keep them out of the drive isles for durability.
Anyhow, I'll take whatever recommendations anyone cares to offer. I've run this by both my mechanical and geotechnial consultants and the responses so far have been less that inspiring.
I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.






RE: Slab on Grade Relief Port Locations
I would think spacing and locations should be discussed concurrently with both the mech and geo guys as it would be a function of the amount of water expected, the flow rate through this relief port etc.
RE: Slab on Grade Relief Port Locations
Professional and Structural Engineer (ME, NH)
American Concrete Industries
www.americanconcrete.com
RE: Slab on Grade Relief Port Locations
The valve's supposed to pop out under some amount of buoyant pressure that would be seemingly impossible to calculate accurately.
As logical as that sounds, it's invariably fruitless. It's about like trying to get other consultants to participate in the dreaded weeping tile discussion.
Commonly used in my area for "by the river" projects. In theory, there's to be 750 gallons per minute flowing through the basement. And that value was reduced five fold post begging. Basement should probably be tanked if we really expect all that wah-wah.
I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.
RE: Slab on Grade Relief Port Locations
Spacing was always a guess since we could not get info from our geotech (although they should have the ability to calculate required pressures).
RE: Slab on Grade Relief Port Locations
I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.
RE: Slab on Grade Relief Port Locations
You would have to install the swimming pool relief valves in boxes, probably the drainage pits.
RE: Slab on Grade Relief Port Locations
Because this is what's commonly done in my locale. Now let's focus and help KootK with the questions that were asked:
1) Spacing
2) Preferred locations.
I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.
RE: Slab on Grade Relief Port Locations
I also think a ten foot grid in addition to that would work well.
Mike McCann, PE, SE (WA)
RE: Slab on Grade Relief Port Locations
RE: Slab on Grade Relief Port Locations
Dave
Thaidavid
RE: Slab on Grade Relief Port Locations
It really does. Let's not kid ourselves though: precedent underpins the bulk of human achievement. Were I raised by wolves, I'd likely not have figured out fork technology yet alone hydrostatic relief ports.
This was my guess too. First pass was 4' away from all of the floor drains. Getotech came back with some guidance to the the tune of about twice this much, a little closer to Mike's recommendation. It forced me to put a few in drive isles which I was trying to avoid, rightly or wrongly.
Yes, we have exactly this in addition to everything else. Our sump is 2m x 4.5m x 2m deep. It's rough as we're between two existing basements and it's messing with footing elevations pretty badly.
I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.