I'm looking at installing 3 stand alone MCC panels in an existing small room at a process plant. They measure 2.5 feet wide and vary between 16 to 24 feet long: controls for about 30 motors with 3 VFD's. Access is only through a doorway. My questions are: 1) are the units normally shipped in one piece 2)can these units be shipped in smaller sections and assembled in place? Is this practical or too labor intensive? 2) consider an alternate route by cutting a hole in the roof?






RE: MCC room construtability
This can be done on site and is no problem.
The roof is safe!
(I presume you are in the USA by your use of imperial measurements, you only mention one doorway, in the UK we need an escape door also so that there are different escape routes, does your room have one? I don't know the USA rules but you will probably need one).
RE: MCC room construtability
RE: MCC room construtability
RE: MCC room construtability
RE: MCC room construtability
RE: MCC room construtability
Also assuming that you are in the US or Canada.
I for one am confused. "They measure 2.5 feet wide and vary between 16 to 24 feet long: ..." Are these dimensions for the MCCs or for the room?
If for the room you may not be able to utilize those spaces to house electrical equipment at all. Code will require a minimum of 36" clear space IN FRONT of the equipment to the nearest wall or structure. The shallowest MCC I know of is 14" deep (Furnas / Siemens).
If those dimensions are for the MCCs, why are you asking since it sounds as if they are already built? If so, can't the manufacturer tell you if they can be split up?
Just a thought to help you avoid unnecessary trouble.