Pipelines are going to be placed in a trench of 4 m wide. The invert of pipes would be 5 m below the surface ground elevation. Ground is sandy silt (SPT=11), clayey silt (SPT=17), clayey sand (SPT=4) and below 7 m depth silty sand (SPT=15). Groundwater table is high.
We are using pre-fab cage with steel plates.
Could someone please advise 1-2 references/design manual to design the above trench - including heave, embedment length. Thank you very much.
We are using pre-fab cage with steel plates.
Could someone please advise 1-2 references/design manual to design the above trench - including heave, embedment length. Thank you very much.





RE: Trenching for pipelines
Potential quick conditions from groundwater. Be careful of sand layer at bottom. Assume you will dewater well below this level.
RE: Trenching for pipelines
RE: Trenching for pipelines
Wonder if there is a more recent reference which may take all the above into account. Thank you.
RE: Trenching for pipelines