INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Permeable Pavement

Permeable Pavement

Permeable Pavement

(OP)
Good afternoon Engineers!

I am currently working on the design of a flexible permeable pavement, (first time doing so). The reason to implement this material is to minimize, even eliminate, stormwater runoff.

According to TxDOT, I was able to come up with most variables except the Mr (Resilient Modulus) for the two-layer system.

The in-situ soil is a Sandy Soil (USC Soil Type SM).
I can easily come up with Mr if I were to follow the following equations;
1) Mr = 2555 x (CBR)^0.64
2) Mr = 1500 x (CBR)

The problem I am running into is that I can not get accurate and/or reliable CBR values for (1) No.57 aggregate with 40% void ratio for the reservoir layer and (2) the flexible permeable top layer.
Also, the Mr values do change depending on the Wet and Dry season.
Any guidance related to the change due to wet/dry season would be appreciated.

Thank you so much!

RE: Permeable Pavement

You will have to get the reservoir layer tested for CBR. For the asphalt layer, find a Mr for an open graded friction course...will likely be close. Since your permeable layer also serves as a structural layer, you might have a need for more thickness than you might think, depending on traffic.

Also, I would caution against thinking you will have no runoff. Pervious pavements get overwhelmed quickly in short duration, high intensity rainfall so runoff is inevitable. Further, debris infiltation will clog the pervious pavement with time and you will have even more runoff.

Great to get you through an approval process.....not so much for long term performance.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources