INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

JAcking system on Floating Roof Tank

JAcking system on Floating Roof Tank

JAcking system on Floating Roof Tank

(OP)
Good morning Gents,

It is common for EFRT which is built by using conventional method (shell lifted by crane from shell course#1) that the floating roof is built in parallel with shell courses after completion bottom plate and shell course #1.

How about in jacking system ? I think we have to wait to build the floating roof till all shell are completed erected and welded.

I agree that jacking system will eliminate working at height. But in tank construction something that can be done in parallel will contribute significant effect in squeezing the overall schedule. Also we need a bigger crane to built the roof.

Is there any study that jacking system in overall (safety, schedule and cost) is better than conventional method ?

Your comments is highly appreciated.

Syah




Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources