INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

4 Level addition to concrete building

4 Level addition to concrete building

4 Level addition to concrete building

(OP)
This is a conceptual question.

An existing 4 level concrete building to have 1 level added transfer steel frame and 3 level added timber structures. there is a rigid slab at steel transfer frame level.

As you know it is not possible to model timber building in Etabs.

I thought a implication is to model additional steel transfer frame only with a lumped mass from timber above. I think the mass of 'timber' should be scaled by lever arm because we manually dropping down the centre of mass to the bottom of timber building.

One engineer is arguing that the timber is so flexible, can just lumping the mass without any scale up.

What is your opinion? A sketch is attached for your quick reference.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources