Hardness test for boiler pressure parts welded portion?
Hardness test for boiler pressure parts welded portion?
(OP)
Hi,
I would like to inquire if when are we gonna apply hardness test for boiler pressure parts. We will replace final superheater stub tubes (SA213-TP347H).
Good day.
jba15
I would like to inquire if when are we gonna apply hardness test for boiler pressure parts. We will replace final superheater stub tubes (SA213-TP347H).
Good day.
jba15





RE: Hardness test for boiler pressure parts welded portion?
What does your contract require?
What does your customer require?
When will it happen? We don't know your job's schedule. 8<)
RE: Hardness test for boiler pressure parts welded portion?
RE: Hardness test for boiler pressure parts welded portion?
The contractor only required for the supply of new tubes.
We planned to implement the replacement during our planned maintenance schedule in November 2015. Approximately 20 days period.
Also, in addition, does MT works for SA213-TP347H material? I cannot verify it now, not until the boiler unit is shut down.