×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Segmental Tunnel

Segmental Tunnel

Segmental Tunnel

(OP)
Hi all, I am doing research on the construction method of laying 900mm and 600mm pipe underground by segmental tunnel (maybe referred to hand dig tunnel) which is 2m x 2m x 30m tunnel at 6m depth (invert level). could you let me have your view on which main components should be considered when designing the tunnel? any reference could be made to? grade I rock stratum is encountered at the depth of 2m.

RE: Segmental Tunnel

I know the word rock means different things to different people , and I don't know what the civil / environmental definition of grade 1 rock is , but as a miner, I would NEVER ask men to hand dig thru rock. Are you prepared to be willing to work alongside the guys doing this excavation?? If not , be very carefull how you write the specifications.

RE: Segmental Tunnel

Are you talking cut and cover construction?

RE: Segmental Tunnel

(OP)
hi bimr, thanks for the reference provided. The purpose of installation is for water pipe by segmental tunnel approach in urban area. Because of site constraints caused by traffic condition and congested underground installations, trench in phase is impossible to launch. Thus the segmental tunnel approach is introduced while the space allowed for launching/receiving pit construction is very limited, i.e. 2.5m(w) x 2.4m(L).

to miningman, your concern is understood. given to the above mentioned situation,there is no alternative but hand dug tunnel is likely.

to buggar, cut and cover construction is unlikely due to the site constraint of my concern.

Therefore, I want to make reference to the past experience for drafting my research and to ask what should I have to care about on the design before carrying out the tunnel works. for instance, where are the loadings applied? what is the appropriate safety factor that should be applied?

please let me have all your views. thanks

RE: Segmental Tunnel

Forget hand digging. Focus your research on directional drilling and similar technologies.

RE: Segmental Tunnel

The space allowed for launching/receiving pits would have to substantially larger than 2.5m(w) x 2.4m(L) no matter what technique that you are using.

  • Directional drilling generally does not work in an urban area where it is desired to install the pipe level. You would have too much setback where the pipe enters the ground.
  • Pits as deep as 6 m would require substantial shoring.
  • The pipes are generally not installed in a tunnel.
  • The size of the pipe that you are talking about is also too small for use with a microtunneling machine.


One of the problems that you will encounter is how to make the connection for the service drop for each individual water user. You will have to install another pit to make the connection.

If you are really in the middle of a major city, you would be looking at some type of auger or jacking.

RE: Segmental Tunnel

Do you want to tunnel 30 meters or 30 miles? Just digging 2 access holes would take up 3 times the segment length.

Richard A. Cornelius, P.E.
WWW.amlinereast.com

RE: Segmental Tunnel

(OP)
hi all, thanks for the fruitful hints. finally, much grateful if you could let me have your view again on how to check the stability of the tunnel formed by 2000mm steel casing which is pushed by pipe jacking approach in sandy clay. does it require to check SLS and ULS? and how to assess the adequacy of the factor of safety applied? Thanks

RE: Segmental Tunnel

With your space constraints of 2.5 m by 2.4 m, the casing segments can only be about 1 m in length. The casing is almost as wide as the access pit. No room for shoring/bracing to keep the people at the bottom safe. could you post a plan view of the roadway with the utilities, etc. drawn in? I wonder if this can even be built the way you say you have to. Water pipes are normally 5-6 m long. DIP would be the same and 900 mm pipes will be heavy. you will need a major amount of space on the road for equipment. Cranes, pumps to run the rams for the jacking, trucks to deliver your 1 m pieces of casing and 2 m pieces of the pipe for the services and more I haven't even thought of yet.

Richard A. Cornelius, P.E.
WWW.amlinereast.com

RE: Segmental Tunnel

First you are in some kind of rock, now it is sandy clay. Are you really an engineer? or a student. You should know how to check the ability of your casing to withstand the loads on it.

Richard A. Cornelius, P.E.
WWW.amlinereast.com

RE: Segmental Tunnel

A fairly simple search finds lots of topics under the term "hand tunnelling shield", e.g https://www.facebook.com/media/set/?set=a.49647173...

However your pits are simply too small to be on any use, either to build the tunnel in the first place or insert any pipes in them afterwards. you need one to be at least 5-6m long. If you can't get this, then the technique is not feasible IMHO.

Remember - More details = better answers
Also: If you get a response it's polite to respond to it.

RE: Segmental Tunnel

(OP)
hi dicksewerrat, this is the research of my first year in university to simulate a condition for tunneling works by means of pipe jacking method. from design to construction, the information as detailed as possible shall be made for this research. some reference recommend the preferable condition for tunneling i.e. sandy clay due to its plasticity. for simplification, the change in situation is made. however, there are many questions on the checking of the stability of the tunnel formed by steel casing. it is grateful If you has any good example of similar works for my reference. thanks

hi littleInch, thanks for your hints.

RE: Segmental Tunnel

note that hand excavation is probably not possible for 600mm, 800 - 900 is generally the limit
a square tunnel is possible but probably not feasible, a round steel casing with a carrier pipe inside is a much better design.

main issues to address:

groundwater and dewatering if necessary
affect of water level or lowering of water level on stability of the face and pit walls
existing trenches / utility lines above the tunnel
leaking sewer lines above
allowable settlement so as to not affect everything above
rock, cobbles, boulders and sand or other layers crossed besides just the clay
shoring of jacking and receiving pits
length of jack / cohesion of material / calculation of the jacking force
determine the allowable length between jacking, intermediate stations and receiving pits
design of the foundation and thrust wall for the hydraulic jack
earth load on the pipe
jacking force on the pipe
design of thrust ring
need for mud or grout?
earth load on the jacking shield
what type of shield
slope stability at the face of excavation
removal of material, slurry pipeline, auger, buggies, buckets
curved or straight alignment, tolerance on line and grade

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources