INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

B31.3 and/or CSA Z662 - Pressure/Leak Testing on Threaded Piping

B31.3 and/or CSA Z662 - Pressure/Leak Testing on Threaded Piping

B31.3 and/or CSA Z662 - Pressure/Leak Testing on Threaded Piping

(OP)
Pressure/Leak testing has always confused me and I'm hoping someone can give me the likely easy answer? Testing requirements (the basics) are relatively the same for both B31.3 and CSA Z662 so I assume the answer doesn't change between the two?

I think the answer is simple but thought I would get input. For threaded piping we still need to complete a leak and pressure test? We can test two separate piping assemblies in the shop and then assemble on site...both for flanged and threaded? AND if we have to cut and rethread a portion of the threaded piping, this must be re-pressure tested, correct? Similar to if we cut and reweld a flange on, correct?

As well, in B31.3 we don't have to leak or pressure test drain piping...but in CSA Z662 I believe we still need to complete a leak test, correct?

RE: B31.3 and/or CSA Z662 - Pressure/Leak Testing on Threaded Piping

Another question without any basis.
Where is this project located?
What are the local Codes, Rules, Laws and Standards regarding this subject?
What is the commodity?
What is the Operating Pressure?
What is the Operating Temperature?
What is the Client's position on this subject?
What is the position of the local AI (Authorized Inspector) on this subject?


Sometimes its possible to do all the right things and still get bad results

RE: B31.3 and/or CSA Z662 - Pressure/Leak Testing on Threaded Piping

(OP)
Where is this project located? - My question is just based on B31.3 and Z662, and at this point I'm not looking at any jurisdictional regulations.
What are the local Codes, Rules, Laws and Standards regarding this subject? - As above
What is the commodity? - Normal Fluid Service
What is the Operating Pressure? - >700 kPa
What is the Operating Temperature? - Normal fluid service (say 50C)
What is the Client's position on this subject? - Doesn't matter, I'm looking for an interpretation of the code of fellow forum members.
What is the position of the local AI (Authorized Inspector) on this subject? - Doesn't matter, I'm looking for an interpretation of the code of fellow forum members.

RE: B31.3 and/or CSA Z662 - Pressure/Leak Testing on Threaded Piping

302Hugo,
All joints require leak testing so a cut and rethread would require retesting - whether that is the entire system or an isolated section is up to you.
Cheers,
DD

RE: B31.3 and/or CSA Z662 - Pressure/Leak Testing on Threaded Piping

(OP)
Thanks DekDee. I figured the answer was pretty straight forward but needed some confirmation.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources