INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

UG-22 Checklist for vessel required?

UG-22 Checklist for vessel required?

UG-22 Checklist for vessel required?

(OP)
We design tanks based on general conditions supplied by our customer.
Basic Section VIII tanks with some nozzles.
My AI just recently requested a UG-22 checklist.
I am never provided with these "supplementary" conditions.
What do i tell my AI?
Am I responsible for UG-22 loadings if they are not provided to me?
Am i required to request them?

RE: UG-22 Checklist for vessel required?

You, as the Designer, needs to consider the loading in UG-22. This is fundamental to the design adequacy for any Section VIII, Div 1 stamped pressure vessel.

How you consider is based on what is described in your Quality Manual - this activity can be outsourced under your control or by use of a check sheet or computer software. All it means is that you considered the loads in design.

RE: UG-22 Checklist for vessel required?

(OP)
What if my customer does not have information relative to performing the points listed under UG-22?

What about tank manufacturers that fabricate and sell off the shelf Sect VIII stamped tanks for unknown end applications?

RE: UG-22 Checklist for vessel required?

JAYDEE23, you should, of course, include all reasonable, relevant loadings per UG-22. You should probably not invent loadings that are more severe than actual or are unrealistic. Examples might be seismic loading and wind loading to a standard of your choice. Some might be disregarded, for example wind loading on horizontal vessels is usually negligable.

In a perfect world, the buyer would inform you of all applicable loadings. This rarely happens.

I suspect that your AI is looking for some kind of statement that you have considered UG-22 loadings, even if only informally. I doubt he is looking for anything more than that, i.e the actual calculations.

Regards,

Mike



The problem with sloppy work is that the supply FAR EXCEEDS the demand

RE: UG-22 Checklist for vessel required?

(OP)
SnTMan,
Yes. The AI was not pushing hard for it, just like you said, looking for a statement of consideration. I just have an issue filling out a UG-22 checklist when the reality is i dont have the data required. I suppose requesting it is all i can do.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.