INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

LV breaker testing

LV breaker testing

LV breaker testing

(OP)
I have LV breaker.
I have tested these breaker with both primary and secondary injection testing and all pass.
Now there are setting on the breaker that need to change. example INST need to change from 12x to 4x. Or STPU need to change from 6 to 8 etc.

my question is do i need to retest the breakers?
is there a standard that spells this out?

When an elephant is in trouble even a frog will kick him.

RE: LV breaker testing

Typically changing the settings on a breaker or relay does not warrant a retest unless there are firmware or logic changes that need testing.

RE: LV breaker testing

(OP)
Thank you, is there published information that supports this? I have looked and can not seem to find what i'm looking for

When an elephant is in trouble even a frog will kick him.

RE: LV breaker testing

yes

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources