×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Steel percentage of reinforced concrete beam

Steel percentage of reinforced concrete beam

Steel percentage of reinforced concrete beam

(OP)
Hi everyone!

I am designing a reinforced concrete beam where the required steel percentage is greater than the allowable max steel percentage.
The beam size has been predetermined by the architectural demand which carries a larger moment causing the steel required to go over max allowable steel. I remember my professor once said that if this case happens, then use the max allowable steel to compute for steel area to be furnished. The idea is to prevent over-designing in the member for this will cause unnoticeable or sudden collapse. But my doubt is that the beam may not be able to withstand the applied moment because the steel area required has been lower.

Any input and reference to help enlighten this issue.

RE: Steel percentage of reinforced concrete beam

It sounds like you are on the right track, but you should get some help with this from an experienced engineer.

Too much steel is not good for the reason you described. Too little steel is not good because the strength is too low. So that leaves making the beam larger. You can't always satisfy architects.

RE: Steel percentage of reinforced concrete beam

Your professor's suggested approach sounds terrible to me. You simply wouldn't have enough capacity. If you use ACI 318, you can over reinforce and accept a lower phi value. Otherwise you can supply compression steel to bring the beam back to an under reinforced condition.

You probably do need a larger beam and I imagine that your deflection estimates will bear that out. Are you making use of T-beam action? That can help.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.

RE: Steel percentage of reinforced concrete beam

Agree with KootK... use compression steel to reduce the concrete compressive stress, thus allowing more tension steel to be used. But as KootK says, you probably will have deflection problems.

RE: Steel percentage of reinforced concrete beam

Agree 100% with KootK

RE: Steel percentage of reinforced concrete beam

(OP)
Thanks a lot for giving your valuable inputs. I forgot to mention that he also suggested to follow doubly reinforced procedure which is exactly what everyone has recommended. I went through my professor's handout, it recommends using rho max or 0.9rho max for As1 to get the trial capacity of the section M1, then compute trial As2 = As' (assume still yields; check it later on). If both steel in compression and tension yield, so total steel in tension is As = As1+As'. The use of rho max in this handout is similar to the recommendation given in reinforced concrete design by Jack C. McCormac, however, I have other books which suggest rho = 0.85 f'c B 0.003 / fy (0.005+0.003) for As1, this is to keep phi = 0.9 (0.005 is in the tension-controlled zone) in computing for the capacity. Jack also explains that compression reinforcement can reduce deflection.
Based on your respective experience, which rho value would you like to use to compute for As1?

T-beam is another option to overcome this issue, but personally I am not really convinced to accept the reality that T-beam is safe in the long run for moment resisting frame of a bldg, instead I prefer doubly reinforced rectangular section.

RE: Steel percentage of reinforced concrete beam

Well Normally when you use compression reinforcement to increase tension , you have to make sure many other factors are satisfied,such as

long term deflection.
clear spacing between bars.
congestion of reinforcement at column


better to have a look on possibility of making the beam wider

RE: Steel percentage of reinforced concrete beam

The architect Primary Objective is to make the Building Aesthetically Pleasing, Your Job is to make the building structurally sound....In Limit State design Structural Soundness supercedes Aesthetics. Make the building sound even if it means tweaking the architectural plan a bit in consultation with the architect

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources