delay in the concreting of one of the piles
delay in the concreting of one of the piles
(OP)
Good day,
During the excavation of the piles under a bridge, one of the piles has been excavated and the machine broke down. Therefore, concretre couldnt be placed inside the pile for more than 24 hours. The machine will be fixed this night and today will be ready.
the pile is filled with bentonite though its entire depth. I know that concreting should be placed without delay after the excavation but it was an accident.
Do u think it is ok ?
During the excavation of the piles under a bridge, one of the piles has been excavated and the machine broke down. Therefore, concretre couldnt be placed inside the pile for more than 24 hours. The machine will be fixed this night and today will be ready.
the pile is filled with bentonite though its entire depth. I know that concreting should be placed without delay after the excavation but it was an accident.
Do u think it is ok ?





RE: delay in the concreting of one of the piles
Then they are going to re-drill through the bentonite and the remaining depth and then cast the pile?
I don't necessarily see a large issue with that course of events but I'm no geotech.
RE: delay in the concreting of one of the piles
RE: delay in the concreting of one of the piles
RE: delay in the concreting of one of the piles
RE: delay in the concreting of one of the piles
RE: delay in the concreting of one of the piles
RE: delay in the concreting of one of the piles