INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Slab on Grade - Control Joint Location

Slab on Grade - Control Joint Location

Slab on Grade - Control Joint Location

(OP)
If I have a 20ft x 20ft room with a sump in the middle, is it best to run the control joints diagonally from the corners of the room to the corners of the sump pit?
Or saw cut down the centre with orthogonal pattern?

RE: Slab on Grade - Control Joint Location

For 20 by 20 slab, sawcut the joints within 8 hours of concrete placement and sawcut two joints, to break the slab into 4 equal square sections. Do not saw diagonally. That will cause cracking near the apex of each triangular section.

Sawcuts should be to a depth of 25 percent of the slab thickness.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources