INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

connecting to existing steel with concrete fireproof

connecting to existing steel with concrete fireproof

RE: connecting to existing steel with concrete fireproof

Our company has used a similar note for your situation.
"Remove and replace fireproofing as required."
I'm not sure how contractors typically remove the fireproofing.

RE: connecting to existing steel with concrete fireproof

I second the "remove and replace" wording. How they do it is up to them....contractors are big on touting "means and methods" as their province so let them have that one. Plus, mercy upon your soul if the fireproofing contains some hazardous material and you specifically told them to chip away at it...

RE: connecting to existing steel with concrete fireproof

If you answer my questions below I will supply the repair wordings.

The "fireproofing" to be removed is cast-in-place concrete??

Or, is it light weight cementitious aggregate (LWCA)

Are there older documents/prints that clearly identify the concrete as "fireproofing" with Assemby Rating per specific UL design?

RE: connecting to existing steel with concrete fireproof

if you are intending to coat the new steel that is connected to it, perhaps require the contractor submit a cementious SFRM and require beam pockets to be full.

RE: connecting to existing steel with concrete fireproof

Personally, I do not like using "in kind" for fireproofing. I am not an expert in fire-resisting materials, but when you use the phrase "in kind" you have effectively said "the fire-resisting material which exists is sufficient to be matched by a new application." I don't often feel good about interjecting that opinion (when I am not sure what the material is), and would keep it more vague. I usually say something like "Restore all disturbed steel fire-resistive material per Building Code requirements; retain a qualified and competent Registered Design Professional to specify restoration when required by the Code."

Then again, if it is in your fee to perform the work, and you feel comfortable/familiar with the existing material, you may be able to specify restoration with IBC prescriptive language.

"It is imperative Cunth doesn't get his hands on those codes."

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources