INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

deep excavation level need to be filled before doing the footing

deep excavation level need to be filled before doing the footing

deep excavation level need to be filled before doing the footing

(OP)
is it possible to backfill & compact a depth of 6-8m and then build the footing?

i have a problem in my project, the new received site, the site level have some area levels is lower than the excavation level by 6 to 8m.

is there any methodology supported by international codes ref. such ASTM describe this case.

Please support.

RE: deep excavation level need to be filled before doing the footing

Yes, it's possible. It is called controlled, engineering fill. Must be done properly. It is also expensive to do so. There are no shortcuts. Do it right.

Is it practicable? Only the economics of your project can decide that.

RE: deep excavation level need to be filled before doing the footing

(OP)
thanks for your reply, however the engineer will not agree unless i submit a methodology supported by international codes references.

can you support in such Ref.

RE: deep excavation level need to be filled before doing the footing

No, you'd need a geotechnical engineer that is experienced with the project area as well as engineered fill.

There's no one code reference that will approve or deny the use of 6-8m of controlled fill.

That's a lot of fill though, are you sure that the current site level is 6-8m low? and if so, why does it need to come back up?

I'm envisioning major slope stability issues if your existing site elevations vary by that much.

RE: deep excavation level need to be filled before doing the footing

(OP)
Yes, it is really vary that much as the site is huge.

the Engineer needs from us to:
Unauthorized Excavation: Consists of removal of materials beyond indicated subgrade elevations or dimensions without specific direction of the Engineer. Unauthorized excavation shall be at the Contractor’s expense.
1. Under footings, foundation bases, or retaining walls, fill unauthorized excavation by extending the indicated bottom elevation of the footing or base to the excavation bottom, without altering required top elevation.

actually we did not did unauthorized excavation, but this mistake happen when they firstly receive the site.

RE: deep excavation level need to be filled before doing the footing

If the site currently exists with a 6-8m differential it seems odd that they wouldn't design the building to accomodate it. Hell, that's one large basement you could add.

RE: deep excavation level need to be filled before doing the footing

jayrod...I agree! Geez...why not work with what you have. Ideal situation for entry at higher level, basement or other on lower level. Otherwised properly engineered fill.

RE: deep excavation level need to be filled before doing the footing

Think of all the money you would save by just building basement walls. That engineered fill is going to be pretty expensive. I would bet the cost of a concrete basement would be pretty close to the cost of the fill. It's like a free basement.

RE: deep excavation level need to be filled before doing the footing

I was thinking that, in answer to the first question of compacting uncontrolled fill, if the equipment is in the country, that these systems might be used. Vibroflotation has been used on naturally loose deposits. Also deep compaction has been used on fills with dropping of large weights, dynamic compaction. To evaluate the results, conventional test borings or test pits would verify the adequacy of the work. Of course piles driven through the fill also is an option.

I've used rolling surcharge on dumped fills, sometimes combined with replacing the upper 5 feet or so with compacted fill under footing locations.

RE: deep excavation level need to be filled before doing the footing

6-8m if filling sounds crazy! What is the site? Is it a subdivision with a lot of high spec houses proposed? Seems uneconomical, I would love to see a cross section throught the deepest fill height! Stability will be an issue, a lot of drainage may also be required!

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources