INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

ASME B31.3 "Hill side connections" & ASME VIII Div 1
3

ASME B31.3 "Hill side connections" & ASME VIII Div 1

ASME B31.3 "Hill side connections" & ASME VIII Div 1

(OP)
Scenario: Design Code B31.3. Branch connection to pipe run is hill side.

Code Clause: 304.3.1 (b) (4) “the axis pf the branch intersects the axis of the run”

Problem: B31.3 does not consider hill side branch connections.

Solution: Refer to 304.7.2, but this does not allow calculation to ASME VIII Div 1 which would be the logical method.

Can someone please tell me why one cannot use UG-37 (VIII, Div 1), understand 31.3 doenst allow it, but why?

Surely this is a common connection in the industry with no simple solution?

RE: ASME B31.3 "Hill side connections" & ASME VIII Div 1

3
Some would argue that B31.3 is a rules-based code, so you must follow the rules- period- even when they essentially say "you can't design something which meets the functional requirements". I'd argue that this is giving the code a little too much credit. It is not intended to eliminate the need for engineering judgment- it is intended to set rules of good practice and to permit people who do not have sufficient engineering judgment to build piping that is more or less safe.

Practical people know that the rules which render an ASME VIII-1 pressure vessel safe, can also be applied to the design and fabrication of piping- not blindly, but judiciously with proper engineering judgment and commonsense.

B31.3 doesn't distinguish between a piping branch connection, which must remain safe against potentially very large forces and moments which may be applied on the run pipe by that piping branch, and a non-moment instrument or tubing connection. ASME VIII does make this distinction, allowing instrument branches to be designed differently.

Speak to the owner- I have met few owners who will not permit special connections in piping to be designed and fabricated per ASME VIII. Our own specs spell this out in detail.

RE: ASME B31.3 "Hill side connections" & ASME VIII Div 1

Excellent post mm, a star for you. Do you have a reference to the relevant VIII-1 section that differentiation for instrument (nozzle) connections?

RE: ASME B31.3 "Hill side connections" & ASME VIII Div 1

ASME VIII-1 UW-16(f)(5) and (6) give the circumstances under which a standard fitting such as a half coupling or flange may be attached to the wall of a vessel by means of a single fillet weld made from the outside. That these connections will be used for the connection of instruments, tubing or the like (which will not transmit substantial moments to the connection) is not spelled out in the language of the code, but it is certainly implied in the nature and limitations of the rules.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources