INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

SPT count procedure

SPT count procedure

SPT count procedure

(OP)

Normally here is the SPT published procedure:

The sample tube is driven 150 mm into the ground and then the number of blows needed for the tube to penetrate each 150 mm (6 in) up to a depth of 450 mm (18 in) is recorded. The sum of the number of blows required for the second and third 6 in. of penetration is termed the "standard penetration resistance" or the "N-value".

The software I use asks for penetration up to 24 in. In that case what would be the SPT blow count. 2nd+3rd or 3rd+4th or...

Thank you.

RE: SPT count procedure

Suppose the sampler was 30 inches long, then what? One firm I first worked for used that long a spoon so that they could take continuous samples to 15 feet without doing any casing, or augers on some sites. We used the second and third 6" summary, but may have used different if we saw reason. For the crudeness of the test, it is not anything to get too refined about. What does one do about a recovery length of much less than the depth penetrated? Again a crude method of sampling.

RE: SPT count procedure

I've used both short and long tubes - the SPT value is the 2nd and 3rd 6" counts. The Brits like to count every three inches (75 mm) but still use the 12 inches corresponding from 6 to 18". Why is your software asking anything more than the SPT N value - or is this for developing the office log? If that, try writing zero (0) for the last 6 inches and see if the SPT N value is as per the definition. The software might just be written for 24 inches as some drillers/engineers like the longer spoons.

RE: SPT count procedure

when in doubt you can always read ASTM D 1586.

In summary, BigH and I do it the same way.

f-d

ípapß gordo ainÆt no madre flaca!

RE: SPT count procedure

ONENGINEER,

It would be most appropriate to use the sum of counts from the 2nd and 3rd 6-in drives (from 150mm to 450mm) for your SPT N-Value. Additional counts should be recorded and reported as they provide additional information which could prove useful in your analysis.

- MorganMWright.com

RE: SPT count procedure

F-D and BigH...same here. The additional 6 inches means nothing with respect to the "N" value.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources