INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Required bolt loading for channel head to shell connection with fixed tubesheet in between

Required bolt loading for channel head to shell connection with fixed tubesheet in between

Required bolt loading for channel head to shell connection with fixed tubesheet in between

(OP)
Hello,

I am trying to determine the bolt loading requirements for the channel head to vessel shell connection on one of our heat exchangers. There is a fixed tubesheet between the two flanges.

Searching for an approach to calculate the bolt loading requirements for this type or arrangement has not turned up much. My thought is that I can use BPVC Section VIII Mandatory Appendix 2 to calculate the required loading for the gasket on each side of the tubesheet and then add the two together for a total required bolt load - does this make sense?

Thank you for any input that you may provide.

RE: Required bolt loading for channel head to shell connection with fixed tubesheet in between

DanTh3Man, Appendix 2 has specific provisions for this, a flange pair. See 2-5(a)(2). Also Part UHX-4(c).

Basically the highest required bolt load for each of the flanges, for both operating and gasket seating conditions is calculated. This highest load is then used for design of both flanges. It is essential to account for pass ribs, if any.

Note that this is for design ONLY. Assembly loads (bolt stresses) will generally be higher, sometimes much so.

Regards,

Mike

RE: Required bolt loading for channel head to shell connection with fixed tubesheet in between

(OP)
Thank you for the reply Mike. Now that you have mentioned that paragraph I feel quite silly for missing it.

I am accounting for ribs as per TEMA RGP-RCB-11.7 Pass partition rib area.

I will also look at applying PCC-2 Appendix O to this issue and see what I can come up with.

Regards,

Dan

RE: Required bolt loading for channel head to shell connection with fixed tubesheet in between

Sounds like you're on the right track :)

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources