INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Contract Technical Requirements Terminology for Approval vs. Acceptance

Contract Technical Requirements Terminology for Approval vs. Acceptance

Contract Technical Requirements Terminology for Approval vs. Acceptance

(OP)
QUESTION: Is there defined (documented) for the use of terms such as APPROVE(D)/APPROVAL vs ACCEPT(ED) when used in Buyer (customer) technical contractual criteria for supplier documentation? e.g. industry standard or regulatory authority.

BACKGROUND: I have a question regarding Contract Technical Requirements Terminology for Approval vs. Acceptance.
I work on a EPC (engineering, procurement, and construction) project. I review documents from responsible engineers that will be used as the basis for a purchase order to suppliers of SSCs (structures, systems, and components.) Within these documents we require suppliers to provide us with their internal documentation of their processes and controls as well as design drawings and specifications. These can be commercial off the shelf or design build items. With regard to these provided supplier submittals, the responsible engineer often states that we (will) "APPROVE" the use of this document to fullfill the contract requirements.

I was taught and take the position that when the supplier provides us with their document, we "ACCEPT" the document because we have no approval authority over the document. e.g. Our signature is not on the supplier's document. On the other hand, we "APPROVE" supplier requests to deviate from contract requirements and have a special form/process for doing so. Our signature IS on our form for approval.

This also leads to questions about DESIGN owner (supplier) vs DESIGN AUTHORITY (buyer) because the buyer understand the use of the SSC within the facility for which the buyer is responsible.

Discussion and opinions are welcome but I am looking for documented definitions that I can point to when challenged. (Engineers challenge each other?!? What a ridiculous thought!)
FYI: My work requires me to work within ASME NQA-1. Specifically, commercial grade dedication.

RE: Contract Technical Requirements Terminology for Approval vs. Acceptance

Its my believe that once you accept the document become a part of the approvals, therefore at that time they are the same. If you want better answers you should consult an attorney experienced in contract works.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources