INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Notching W8x21 Top Flange

Notching W8x21 Top Flange

Notching W8x21 Top Flange

(OP)
I have a situation where we need to notch the top flange of a W8x21 flush beam for some immoveable water supply lines (1/2"ø). See attached. The notches will be within 32" of the support with a moment of about 9'-k at that point. The web will be packed out with wood on both sides to support 2x10 floor joists.
I have analyzed it assuming the notched portion is essentially a WT section (ignoring the un-notched flange). Using the section properties of a WT8x13 (which are a pretty nice fit - basically same web and flange), I get a bending stress of 27 ksi. If I assume I cannot get any local buckling of the tip of the tee due to the un-notched flange bracing it, then it should be compact and I can use an allowable bending stress of .66Fy. Does this approach sound reasonable? I checked deflection in my beam program by adding two short segments of WT section properties and it basically did not change. I am, also assuming I can ignore any twisting of the beam from the flange unbalance since it is framed flush.

Thanks

RE: Notching W8x21 Top Flange

That should be fine as it sounds as though LTB is a non-issue. I'd combine both notches into a single cope and radius it so that you reduce stress concentrations.

I would have gone with analyzing the notched portion of the beam as a channel to improve the odds a bit. Six of one, half a dozen of the other..

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.

RE: Notching W8x21 Top Flange

(OP)
Thanks KootK.

RE: Notching W8x21 Top Flange

I can't believe that a competent plumber is not capable of moving a couple of 3/4 inch water lines. maybe get a half-a__sed handyman in to replace the plumber.

Richard A. Cornelius, P.E.
WWW.amlinereast.com

RE: Notching W8x21 Top Flange

Dick, I would assume the lines can't be moved because they are concealed in the wall above.

How big are the water lines? Can you just provide 1" holes to let them run their lines through?

RE: Notching W8x21 Top Flange

(OP)
@dicksewerrat:
Of course they CAN be moved, but it would cause significant disturbance to the second story finishes which is not being renovated. Much cheaper to pay me to come up with a clever solution.

@Canpro - We could do the 1"Ø holes (the lines are 5/8" OD.), but the contractor would have to get them in exactly the right place - which may be asking alot.

RE: Notching W8x21 Top Flange

Hope you get enough for this. Tell the plumber to sleeve the pipes as they go by the flanges. A little water hammer will wear holes in the pipe.

Richard A. Cornelius, P.E.
WWW.amlinereast.com

RE: Notching W8x21 Top Flange

Sleeve the pipes, insulate them so there is no pipe-to-steel corrosion. (More likely with copper hot water pipe to steel flange, but ... we had pinhole leaks in the basement caused by corrosion where the water pipe touched a bracket.

But, if the pipes HAVE to run at that elevation (they can't be bent up a two inches?) then drill the WF through the web, run the pipes though the holes, then re-connect the pipe.

RE: Notching W8x21 Top Flange

(OP)
@dicksewerrat
This is just one aspect of the renovation that I am involved in so I cant gouge them too much. Just curious how much would you charge not including the site visit.

@rakookpe
The beam is going under the bottom of the second story wall so they have to come thru the flange.

RE: Notching W8x21 Top Flange

Ok,
the wall on the second floor is in place and a bearing wall. Where do these water pipes come from? Are they in a headspace above the first floor ceiling? You can't put a couple posts, 6 inches apart down on the first floor. Where do the water lines go to? Fixtures on the 3rd floor?

Richard A. Cornelius, P.E.
WWW.amlinereast.com

RE: Notching W8x21 Top Flange

(OP)
The wall being removed is on the first story. The lines feed the second story bathroom thru the bearing wall above. They extend out of the bottom of the bearing wall. The beam has to be installed tight to the bottom of the subfloor under the bearing wall. As such, there is interference from the lines.

RE: Notching W8x21 Top Flange

I understand better now. Is there a third floor they could get their water from? Where is the waste line for that bathroom?

Richard A. Cornelius, P.E.
WWW.amlinereast.com

RE: Notching W8x21 Top Flange

(OP)
Waste line come out into the joist bay at a different location so it is OK.
There is no third floor.
Even if they could, it is still much cheaper to mess around with the engineering

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources