Nozzle Schedule
Nozzle Schedule
(OP)
Dear Friends,
i have one doubt regarding the selection of nozzle (Pipe neck & Flange) schedule for the API 650 Storage Tanks nozzles.
How to select the schedule of the nozzles?
from API 650, Table 5.6a & 5.6b we will get the Nominal Thickness of Flanged Nozzle Pipe Wall, So with respect to this how will select the schedule.
Thanks in Advance.
i have one doubt regarding the selection of nozzle (Pipe neck & Flange) schedule for the API 650 Storage Tanks nozzles.
How to select the schedule of the nozzles?
from API 650, Table 5.6a & 5.6b we will get the Nominal Thickness of Flanged Nozzle Pipe Wall, So with respect to this how will select the schedule.
Thanks in Advance.





RE: Nozzle Schedule
You choose the respective Pipe Schedule based on ASME B36.10.
Hope this help.
RE: Nozzle Schedule
RE: Nozzle Schedule
Thanks alot